BLD01-01671
| BLD-Final | 11/8/2001 | 11/9/2001 | 11/9/2001 12:00:00 AM | A | NR |
|
|
Scheduled by a contractor via Hello! on 11/08/2001 at 11:23:08. Contact: ###-####. need fire, elec. 11/9/2001 9:27:59 AM
|
BLD01-02088
| BLD-Energy code compliance | 11/8/2001 | 11/9/2001 | 11/9/2001 12:00:00 AM | A | PART |
|
|
###-#### ok to cover , keep c/n...gyp shear, underfloor supports, insul, & vapor barrier; hangers at porch joists, porch roof not framed. chk stairs rails, etc at final. 11/9/2001 12:16:19 PM
|
MEC01-03286
| Pressure Test | 11/8/2001 | 11/9/2001 | 11/9/2001 12:00:00 AM | A | PASS |
|
|
Scheduled by a contractor via Hello! on 11/08/2001 at 15:42:11. Contact: ###-####. med press ok at 60# 11/9/2001 12:16:43 PM
|
BLD01-02607
| BLD-Conference | 11/8/2001 | 11/9/2001 | 11/9/2001 12:00:00 AM | A | PART |
|
|
Scheduled by a contractor via Hello! on 11/08/2001 at 19:32:37. Contact: ###-####...req'd arch/ eng'r to report or provide spec insp for bolts installed in masonry & steel fabrication. 11/9/2001 10:33:13 AM
|
BLD01-02523
| BLD-Framing/Rough-in | 11/9/2001 | 11/9/2001 | 11/9/2001 12:00:00 AM | A | PART |
|
|
Scheduled by a contractor via Hello! on 11/09/2001 at 07:08:23. Contact: ###-####. c/n, ok to side exc at patio, need analysis re deleted sw. 11/9/2001 12:09:31 PM
|
BLD01-02191
| BLD-Conference | 11/9/2001 | 11/9/2001 | 11/9/2001 12:00:00 AM | A | PART |
|
|
Basement ceiling height approved as is.
|
BLD01-02433
| BLD-Framing/Rough-in | 11/7/2001 | 11/9/2001 | 11/9/2001 12:00:00 AM | A | PASS |
|
|
###-#### ok to cover, chk comb air at final. 11/8/2001 5:21:57 PM
|
BLD00-03538
| BLD-Footing | 11/9/2001 | 11/9/2001 | 11/9/2001 12:00:00 AM | P | PASS |
|
|
Added by Inspector: 340 On 11/9/2001 4:36:33 PM w/ arch and Robin Carnes at site re stair enclosure...no extra penetrations allowed; provide 2hr assy for hydraulic line.
|
BLD00-01649
| BLD-Conference | 11/9/2001 | 11/9/2001 | 11/9/2001 12:00:00 AM | P | PASS |
|
|
Added by Inspector: 340 On 11/9/2001 4:38:27 PM onsite w/ Mel P. re req's for fire doors/rated glazing...90 min req'd at 2hr wall sections.
|
BLD01-00594
| BLD-Energy code compliance | 11/9/2001 | 11/9/2001 | 11/9/2001 12:00:00 AM | P | PART |
|
|
Added by Inspector: 340 On 11/9/2001 5:00:39 PM ext walls ok; need chk 3rd fl draft stop seal, rest ok to begin cover.
|
BLD01-00594
| BLD-Wall cover | 11/9/2001 | 11/9/2001 | 11/9/2001 12:00:00 AM | P | NR |
|
|
Scheduled by a contractor via Hello! on 11/09/2001 at 10:02:33. Contact: ###-####.
|
BLD00-03538
| BLD-Concrete | 11/9/2001 | 11/9/2001 | 11/9/2001 12:00:00 AM | P | PART |
|
|
###-#### pt deck, pend reports. 11/9/2001 4:36:59 PM
|
BLD01-02854
| BLD-Footing | 11/9/2001 | 11/9/2001 | 11/9/2001 12:00:00 AM | P | PART |
|
|
Scheduled by a contractor via Hello! on 11/09/2001 at 10:55:19. Contact: ###-####. ret wall, part ftgs only 11/9/2001 2:40:57 PM
|
MEC01-03330
| Final | 11/8/2001 | 11/9/2001 | 11/8/2001 12:00:00 AM | A | CANC |
|
|
Scheduled by a contractor via Hello! on 11/08/2001 at 09:02:39. Contact: ###-####. Disp set to [CANC] by a contractor via Hello! on 11/08/2001 at 10:42:38.
|