FIR07-00546
| INSP-Conference | 11/8/2007 | 11/9/2007 | 11/9/2007 4:10:32 PM | A | DONE |
|
|
I spoke to mike, the superintendant, about the combustible concealed spaces located around the exterior of the building. They are required to be sprinklered per NFPA 4.1 unless the meet one of the exceptions of 8.14
|
FIR07-00761
| INSP-Sprinkler Rough-in/Hydro | 11/9/2007 | 11/9/2007 | 11/9/2007 3:58:22 PM | P | PASS |
|
|
See the city approved plans where the overhead piping is ok to cover.
|
BLD05-00633
| FIRE-Final Inspection | 11/8/2007 | 11/9/2007 | 11/9/2007 3:56:45 PM | A | PART |
|
|
The 4th and 5th floors of the central tower are ok to occupy. The interconnections at teh 4th and 5th floors to the north tower are not complete yet and are to be blocked off until work is complete.
|
FIR06-00011
| INSP-Alarm Testing | 11/8/2007 | 11/9/2007 | 11/9/2007 3:54:36 PM | A | DONE |
|
|
The fire alarm testing of the 4th and 5th floors of the central tower are complete. The 4th and 5th floor connections to the north tower are not complete.
|
BLD06-03140
| FIRE-Final Inspection | 11/9/2007 | 11/9/2007 | 11/9/2007 1:23:04 PM | P | PASS |
|
|
life safety passed.
|
FIR07-00386
| INSP-Alarm Testing | 11/8/2007 | 11/9/2007 | 11/9/2007 1:22:28 PM | A | CANC |
|
|
To be rescheduled for tuesday since the fire alarm contractor could not make the 8:00am meeting time.
|
BLD06-02010
| FIRE-Conference | 11/8/2007 | 11/9/2007 | 11/9/2007 1:22:10 PM | A | CANC |
|
|
To be rescheduled for tuesday since the fire alarm contractor could not make the 8:00am meeting time.
|
BLD07-02909
| FIRE-Final Inspection | 11/8/2007 | 11/9/2007 | 11/9/2007 1:21:02 PM | A | PART |
|
|
A temporary occupancy was given until the exit signs/emergency lights are either repaired or removed since they are not required.
|