BLD95-00151
| INSP - Roof | 12/1/1995 | 12/1/1995 | 12/1/1995 12:00:00 AM | | PASS |
|
|
/ / 342 -
|
BLD95-00151
| INSP - Windows | 12/1/1995 | 12/1/1995 | 12/1/1995 12:00:00 AM | | PASS |
|
|
/ / 342 -
|
BLD95-00151
| INSP - Final | 12/1/1995 | 12/1/1995 | 12/1/1995 12:00:00 AM | | PASS |
|
|
/ / 342 -
|
BLD1056006
| INSP - Energy code compliance | 12/1/1995 | 12/1/1995 | 12/1/1995 12:00:00 AM | | PASS |
|
|
/ / 342 -
|
BLD95-01210
| INSP - Wall cover | 12/1/1995 | 12/1/1995 | 12/1/1995 12:00:00 AM | | PASS |
|
|
/ / 342 - 1 hr wall east side ok
|
BLD95-01704
| INSP - Energy code compliance | 12/1/1995 | 12/1/1995 | 12/1/1995 12:00:00 AM | | PASS |
|
|
/ / 342 -
|
BLD95-01855
| INSP - Foundation | 11/30/1995 | 12/1/1995 | 12/1/1995 12:00:00 AM | A | PASS |
|
|
11/30/95 342 - REINSPECT
|
BLD95-01855
| INSP - Footings | 11/30/1995 | 12/1/1995 | 12/1/1995 12:00:00 AM | A | PASS |
|
|
11/30/95 342 -
|
BLD1055016
| INSP - Final | 11/30/1995 | 12/1/1995 | 12/1/1995 12:00:00 AM | A | NR |
|
|
11/30/95 342 - APPOINTMENT BETWEEN 8:30-9 AM. called Carl. Plans to be on site, but could not find. Treat all 1 hr wal penetrations, bring door up to code from boiler rm., need letter from th architect, fire dept, mech and elect insp done.
|
BLD95-01704
| INSP - Framing/Rough-in | 11/30/1995 | 12/1/1995 | 12/1/1995 12:00:00 AM | A | PASS |
|
|
11/30/95 342 -
|
BLD1056006
| INSP - Framing/Rough-in | 11/30/1995 | 12/1/1995 | 12/1/1995 12:00:00 AM | A | PASS |
|
|
11/30/95 342 -
|
BLD95-00592
| INSP - Foundation | 11/30/1995 | 12/1/1995 | 12/1/1995 12:00:00 AM | A | PASS |
|
|
12/01/95 342 - RETAINING WALLS & PIERS.....POURING AROUND 10 A.M. piers ok'd by 342, not ready this am
|