BLD98-02218
| INSP - Framing/Rough-in | 12/1/1998 | 12/1/1998 | 12/10/1998 12:00:00 AM | P | FAIL |
|
|
12/01/98 301 - CORR-CORREC-CALL FOR REINSP WHEN COMPLETED special insp o
|
BLD98-02293
| INSP - Framing/Rough-in | 12/1/1998 | 12/1/1998 | 12/2/1998 12:00:00 AM | P | PART |
|
|
12/01/98 301 - revision from arch to address ceilling assembly forth com
|
MEC98-02935
| INSP - Framing/ Rough-in | 12/1/1998 | 12/1/1998 | 12/2/1998 12:00:00 AM | P | FAIL |
|
|
12/01/98 301 - trans to d lightfoot
|
MEC98-03879
| INSP - Framing/ Rough-in | 12/1/1998 | 12/1/1998 | 12/2/1998 12:00:00 AM | P | FAIL |
|
|
12/01/98 301 - CORR-CORREC-CALL FOR REINSP WHEN COMPLETED
|
BLD97-01410
| INSP - Framing/Rough-in | 11/30/1998 | 12/1/1998 | 12/1/1998 12:00:00 AM | A | PART |
|
|
12/01/98 301 - work inprogess ok
|
MEC98-04080
| INSP - Final | 12/1/1998 | 12/1/1998 | 12/1/1998 12:00:00 AM | P | PASS |
|
|
12/01/98 301 - FNL -OK FINAL
|
MEC98-04080
| INSP - Final | 12/1/1998 | 12/1/1998 | 12/1/1998 12:00:00 AM | P | PASS |
|
|
12/01/98 301 - FNL -OK FINAL
|
BLD98-03576
| INSP - Foundation | 12/1/1998 | 12/1/1998 | 12/1/1998 12:00:00 AM | P | PART |
|
|
12/01/98 301 - footing ok rebar ok compaction report recieved and approv
|
BLD98-01860
| INSP - Framing/Rough-in | 11/30/1998 | 12/1/1998 | 12/19/1980 12:00:00 AM | A | PASS |
|
|
12/01/98 301 - FRAM-OK FRAMING insulation ok
|
BLD98-02110
| INSP - Framing/Rough-in | 11/30/1998 | 12/1/1998 | 12/19/1980 12:00:00 AM | A | PASS |
|
|
12/01/98 301 - both entrys ok for cover.
|
BLD98-02953
| INSP - Foundation | 11/30/1998 | 12/1/1998 | 12/19/1980 12:00:00 AM | A | PART |
|
|
12/01/98 301 - slab s/e site ok for cover 2500 psi design.
|