BLD99-02195
| BLD-Foundation | 11/30/1999 | 12/1/1999 | 12/1/1999 12:00:00 AM | A | PART |
|
|
Scheduled by a contractor via Hello! on 11/30/1999 at 08:10:45. Contact: . Placed w/spec. insp. Pending report.
|
BLD98-01941
| BLD-Final | 11/30/1999 | 12/1/1999 | 12/1/1999 12:00:00 AM | A | PASS |
|
|
Final reinspect - Cathy has the card
|
BLD99-02327
| BLD-Framing/Rough-in | 11/30/1999 | 12/1/1999 | 12/1/1999 12:00:00 AM | A | PART |
|
|
Scheduled by a contractor via Hello! on 11/30/1999 at 14:04:47. Contact: ###-####. Placed masonary grout w/special insp. Pending report.
|
BLD99-02327
| BLD-Framing/Rough-in | 11/30/1999 | 12/1/1999 | 12/1/1999 12:00:00 AM | P | PART |
|
|
Scheduled by a contractor via Hello! on 11/30/1999 at 14:05:53. Contact: ###-####. Rebar & weld plates ok pending report for grout.
|
BLD99-02669
| BLD-Footing | 11/30/1999 | 12/1/1999 | 12/1/1999 12:00:00 AM | P | FAIL |
|
|
Scheduled by a contractor via Hello! on 11/30/1999 at 14:07:19. Contact: ###-####. C/N soil eng. To investigate NW corner to not cover this area w/ft. or Pad ft.
|
BLD99-02416
| BLD-Framing/Rough-in | 12/1/1999 | 12/1/1999 | 12/1/1999 12:00:00 AM | P | PART |
|
|
fire wall bryan ###-#### First layer 2hr wall gyp. Ok P/L wall/North.
|
BLD98-02492
| BLD-Framing/Rough-in | 12/1/1999 | 12/1/1999 | 12/1/1999 12:00:00 AM | P | PART |
|
|
MEL ###-#### Work in progress Idems for engineers review in RFI.
|
BLD99-01816
| BLD-Framing/Rough-in | 12/1/1999 | 12/1/1999 | 12/1/1999 12:00:00 AM | P | PART |
|
|
PARTIAL FRAMING MEL ###-#### Work in progress, straps to roof in place teco nails verify plan/ TJI roof support North/East not appropriate insulation/ beam pocket.
|
BLD99-03493
| BLD-Framing/Rough-in | 12/1/1999 | 12/1/1999 | 12/1/1999 12:00:00 AM | P | PASS |
|
|
ALAN ###-#### Wall bracing to roof struc. Check on final.
|