BLD99-03395
| BLD-Foundation | 11/30/1999 | 12/1/1999 | 12/1/1999 12:00:00 AM | A | PASS |
|
|
wall insp---jake ###-#### ext 17145 mobile # Done on 11/30/99.
|
BLD99-02589
| BLD-Framing/Rough-in | 11/30/1999 | 12/1/1999 | 12/1/1999 12:00:00 AM | A | FAIL |
|
|
Scheduled by a contractor via Hello! on 11/30/1999 at 16:24:18. Contact: . Still has correctioins with new engineering.
|
BLD99-02589
| BLD-Wall cover | 11/30/1999 | 12/1/1999 | 12/1/1999 12:00:00 AM | A | FAIL |
|
|
Scheduled by a contractor via Hello! on 11/30/1999 at 16:24:44. Contact: . Still has corrections.
|
BLD99-02603
| BLD-Framing/Rough-in | 11/30/1999 | 12/1/1999 | 12/1/1999 12:00:00 AM | A | PASS |
|
|
Scheduled by a contractor via Hello! on 11/30/1999 at 16:25:31. Contact: .
|
BLD99-02603
| BLD-Wall cover | 11/30/1999 | 12/1/1999 | 12/1/1999 12:00:00 AM | A | PASS |
|
|
Scheduled by a contractor via Hello! on 11/30/1999 at 16:26:03. Contact: .
|
BLD99-01841
| BLD-Framing/Rough-in | 12/1/1999 | 12/1/1999 | 12/1/1999 12:00:00 AM | P | PART |
|
|
Scheduled by a contractor via Hello! on 12/01/1999 at 08:05:46. Contact: ###-####. Shear nailing ok, need floor to floor St. straps.
|
BLD99-03446
| BLD-Footing | 12/1/1999 | 12/1/1999 | 12/1/1999 12:00:00 AM | P | PASS |
|
|
eric ###-#### or ###-#### ft insp
|
BLD99-03450
| BLD-Footing | 12/1/1999 | 12/1/1999 | 12/1/1999 12:00:00 AM | P | PASS |
|
|
JAY ###-####
|
BLD99-03444
| BLD-Foundation | 12/1/1999 | 12/1/1999 | 12/1/1999 12:00:00 AM | P | PASS |
|
|
FOUNDATION WALL JAY ###-####
|
BLD99-03321
| BLD-Framing/Rough-in | 12/1/1999 | 12/1/1999 | 12/1/1999 12:00:00 AM | P | FAIL |
|
|
tom--- ###-####
|
BLD99-02639
| BLD-Wall cover | 12/1/1999 | 12/1/1999 | 12/1/1999 12:00:00 AM | P | PASS |
|
|
Scheduled by a contractor via Hello! on 12/01/1999 at 10:54:00. Contact: ###-####.
|