Inspections for the day of: Monday, December 1, 2008.
Number of inspections: 11
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorBob Reichert
TitleELE-INSPECTOR
Phone #794-1923
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
ESC08-00152 General Inspection12/1/200812/1/200812/1/2008 3:51:32 PMPPASS
looked ok
ESC06-01236 Site Final12/1/200812/1/200812/1/2008 3:15:29 PMPPASS
looked ok, ok to final
ESC07-01432 General Inspection12/1/200812/1/200812/1/2008 2:59:28 PMAPASS
looked ok
ELE08-02747 Conference12/1/200812/1/200812/1/2008 2:56:15 PMPDONE
michelle - conference - later afternoon please Phone #: ###-#### told owner if ready for final, needed to finish all work and call in for inspection
ELE08-01862 Final11/30/200812/1/200812/1/2008 1:49:29 PMPPART
Phone #: ###-#### Internet Inspection Request from: Jim Williams left correction notice,BCC shall finish elevator before final, signed t/o card, rest ok to final, check for pit lighting, receptacle,
ELE07-00738 Final11/26/200812/1/200812/1/2008 12:50:12 PMPPASS
call Brandon for access to house. Phone #: ###-#### Internet Inspection Request from: Brandon Blackham ok to final
ELE08-00044 ELE-Aging Inspection12/1/200812/1/200812/1/2008 9:56:34 AM DONE
suc per contractor, no esc this project
ELE08-00090 ELE-Aging Inspection12/1/200812/1/200812/1/2008 9:54:17 AM DONE
suc, per permit activity for bld, no esc this project
ELE08-02423 Electrical Rough-In11/26/200812/1/200812/1/2008 9:26:57 AMANH
JASON BLD 3 L1 UNITS D EAST, D WEST & B1 CEILING COVER Phone #: ###-#### Internet Inspection Request from: Sean DeLacy called, left message, called office, not on site, told they need to reschedule when ready, fee due
ELE08-03088 Electrical Rough-In11/26/200812/1/200812/1/2008 8:54:29 AMAPASS
Phone #: ###-#### Internet Inspection Request from: Barbara Szurgot clouds and walls only ok to cover, called to see u/g before cover, no esc this project
ELE08-03123 Final11/26/200812/1/200812/1/2008 8:14:30 AMAPASS
wire outlet for projector--early morning for inspection is best Phone #: ###-#### Internet Inspection Request from: PAT MILLER called contractor, ok to final, no esc this project