Inspections for the day of: Monday, December 1, 2008.
Number of inspections: 20
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorClint A Smith
TitleEROSION CONTROL INSPECTOR
Phone #794-8996
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
ESC08-00906 General Inspection12/1/200812/1/200812/2/2008 10:03:00 AMPPART
Minor trash clean up around the project area.
ESC08-01019 INSP - Stop Work Order12/1/200812/1/200812/1/2008 8:32:34 PMAFAIL
Working with out permit issued. Stop work order issued. No work shall be completed until Permit is issued and all wood chips and tracking is cleaned up off of all hard surfaces.
ESC04-00882 DOC - Permit Expired12/1/200812/1/200812/1/2008 4:33:11 PMPPASS
ESC03-00949 Site Final12/1/200812/1/200812/1/2008 4:32:10 PMPPASS
ESC08-00464 Random Inspection12/1/200812/1/200812/1/2008 4:24:36 PMPPASS
ESC05-02075 DOC - Permit Expired12/1/200812/1/200812/1/2008 3:51:59 PMPPASS
ESC05-01944 Site Final12/1/200812/1/200812/1/2008 3:50:34 PMPPASS
ESC04-00979 Site Final12/1/200812/1/200812/1/2008 3:50:22 PMPPASS
ESC04-00604 Site Final12/1/200812/1/200812/1/2008 3:49:47 PMPPASS
ESC07-00121 Site Final12/1/200812/1/200812/1/2008 3:48:52 PMPPASS
ESC07-00410 Site Final12/1/200812/1/200812/1/2008 3:47:45 PMPPASS
ESC07-00126 Site Final12/1/200812/1/200812/1/2008 3:42:23 PMPPASS
ESC07-00904 Random Inspection12/1/200812/1/200812/1/2008 2:37:28 PMPPASS
ESC08-00617 Random Inspection12/1/200812/1/200812/1/2008 1:59:27 PMPFAIL
Verbal correction to RP:
1. Clean up sidewalks of all sediment and debris.
3. Extend the straw wattle at the bottom of the hill to the south. Will re-inspect on 12/4/08.
ESC08-00927 General Inspection11/28/200812/1/200812/1/2008 1:42:16 PMPPASS
ESC08-00820 BMP Violation11/26/200812/1/200812/1/2008 1:22:54 PMAPASS
Provided a trailer instead of a a trash container.
ESC08-00539 Random Inspection12/1/200812/1/200812/1/2008 11:18:48 AMPPART
Discussed with RP over the placement of the stock pile in the North East corner of project area. Since the stock pile mass is very large and is less than 10ft away from the hinge of the slope down to Chinden Blvd, I am requiring sediment and erosion protection on the stock pile. Will re-inspect on 12/5/08 PM.
ESC05-00045 Random Inspection12/1/200812/1/200812/1/2008 10:50:04 AMAPASS
ESC07-00003 Tracking Control11/28/200812/1/200812/1/2008 10:05:55 AMAPART
Told Rp that they need to clean up the entrance into the parking lot by the end of the day and there intial clean up from last week was a good effort.
ESC08-00758 General Inspection11/28/200812/1/200812/1/2008 10:01:15 AMAFAIL
Spoke with the General Contractor (C&A Paving to protect 2 storm drains and to protect any stock pile staged on the asphalt where any run off could reach any storm drains. Will re-inspect 12/2/08