FIR16-00540
| INSP-Final Inspection | 11/30/2016 | 12/1/2016 | 12/1/2016 12:09:52 PM | A | CANC |
|
|
Coltan Phone #: ###-####
|
FIR16-00441
| INSP-Sprinkler Rough-in/Hydro | 11/30/2016 | 12/1/2016 | 12/1/2016 10:34:13 AM | A | PASS |
|
|
Overhead hydro test passed
|
BLD16-01452
| FIRE-Final Inspection | 11/30/2016 | 12/1/2016 | 12/1/2016 8:54:50 AM | A | PART |
|
|
A temporary for the life safety is being given until the new PIV has been installed which is scheduled to arrive on 12/7/16
|
FIR16-00651
| INSP-Final Inspection | 12/1/2016 | 12/1/2016 | 12/1/2016 8:51:23 AM | P | PASS |
|
|
Permit finaled
|
FIR16-00651
| INSP-Alarm Testing | 11/30/2016 | 12/1/2016 | 12/1/2016 8:49:12 AM | A | PASS |
|
|
Permit finaled
|