ELE03-01760
| Extend Permit 180 days | | 12/10/2003 | 12/10/2003 12:00:00 AM | | DONE |
|
|
OK TO EXTEND PERMIT 180 DAYS PER JIM SCHMER 12-10-03 ///DLD
|
ELE03-03568
| Rough-In Permanent Service | 12/10/2003 | 12/10/2003 | 12/10/2003 12:00:00 AM | P | PASS |
|
|
Concrete over ufer; Phone #: ###-#### Internet Inspection Request from: Dan Rohl
|
ELE03-01760
| ELE-Request for Extension | 12/10/2003 | 12/10/2003 | 12/10/2003 12:00:00 AM | P | PASS |
|
|
work still in progress-- janice-- ###-#### called and left message, permit is extended for 30 days only. Owner's son said he was going to wait until the last minute to do work, so permit is extended for 30 days only. If no work commenced by then, further action will be taken at that time. 12/10/2003 9:57:30 AM
|