Inspections for the day of: Friday, December 10, 2010.
Number of inspections: 16
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorTroy Cobbley
TitleFIRE INSPECTOR
Phone #794-9483
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
MIS10-00330 FIR-Conference12/10/201012/10/201012/15/2010 7:48:26 AMPDONE
This inspection has been deferred to Tom Gainer with the Boise Fire Dept. for follow up. I also spoke to Mark Sentenno.
FIR04-00376 INSP-Final Inspection12/10/201012/10/201012/13/2010 2:36:34 PMPPASS
permit finaled
FIR03-00510 INSP-Final Inspection12/7/201012/10/201012/10/2010 2:58:34 PMACANC
Wrong inspection called in. This one is to be scheduled for next week.
FIR10-00300 INSP-Conference12/9/201012/10/201012/10/2010 2:30:23 PMADONE
I met with Mark from Shilo and we discussed the underground supply line being buried with out any inspections. I left a correction notice referencing IFC 106.2 and 106.3
FIR10-00514 INSP-Sprinkler Rough-in12/9/201012/10/201012/10/2010 2:28:39 PMAFAIL
The insulation in the combustible concealed space does not meet 2010 NFPA 13 - 8.15.1.2.17. Blow-in insulation has been used not the batt insulation as required.
BLD10-01138 FIRE-Final Inspection12/9/201012/10/201012/10/2010 2:27:24 PMACANC
Ron wanted to perform this inspection with Forrest but we went over general life safety items such as when the wall were removed that fire alarm coverage and sprinkler head coverage may have been effected.
BLD10-02686 FIRE-Final Inspection12/9/201012/10/201012/10/2010 2:24:56 PMAFAIL
Provide sprinkler protection in both coolers. Provide access to the fire sprinkler riser and the fire alarm panel so that annual inspections can be verified.
FIR10-00490 INSP-Final Inspection12/9/201012/10/201012/10/2010 2:01:08 PMAFAIL
See the city approved plans for the locations of the deficiencies. They include adding a/v coverage in Offices 105 and 106, providing coverage at the end of a corridor where an existing a/v had been removed, relocating a smoke detector located too close to a supply air diffuser, and setting the correct candella for a strobe in the Vontrol Room on the existing side of this building. No devices were tested. Per plan review as-builts can be provided for the changes.
BLD10-01201 FIRE-Final Inspection12/9/201012/10/201012/10/2010 1:57:46 PMAFAIL
II just went over general life safety requirements with Ron since the project related fire alarm permit has failed inspection. One item that was noticed was that on two sliding doors, non-compliant hardware was installed. Ron stated he would remove all of the locking hardware.
FIR04-00375 INSP-Final Inspection12/7/201012/10/201012/10/2010 11:58:51 AMAPASS
Permit finaled. The hood suppression system functioned correctly. Alex Phone #: ###-####
FIR04-00374 INSP-Final Inspection12/7/201012/10/201012/10/2010 11:58:05 AMAPASS
Permit finaled. The hood suppression system functioned correctly. Alex Phone #: ###-####
FIR03-00381 INSP-Final Inspection12/7/201012/10/201012/10/2010 11:57:15 AMAPASS
Permit finaled. The hood suppression system functioned correctly.
BLD10-02647 FIRE-Final Inspection12/9/201012/10/201012/10/2010 11:55:51 AMAPASS
life safety passed
FIR10-00600 INSP-Final Inspection12/9/201012/10/201012/10/2010 11:52:24 AMAPASS
permit finaled
FIR10-00615 INSP-Final Inspection12/10/201012/10/201012/10/2010 12:00:00 AMPCANC
John Phone #: ###-####
BLD10-02572 FIRE-Final Inspection12/8/201012/10/201012/9/2010 2:51:44 PMAFAIL
Provide panic hardware on the door and provide verification that the visual effect from the nearby fire alarm devices can be seen within this new room.