Inspections for the day of: Monday, December 10, 2018.
Number of inspections: 10
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorEric Story
TitleELE-INSPECTOR
Phone #985-3493
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
ELE12-01237 ELE-Aging Inspection12/10/201812/10/201812/18/2018 12:23:35 PM CANC
Too busy
ELE13-00519 ELE-Aging Inspection12/10/201812/10/201812/18/2018 12:23:19 PM CANC
Too busy
ELE18-04385 Final12/10/201812/10/201812/10/2018 3:47:21 PMPCANC
For access please call Ed 1/2 hr prior to inspection.###-#### Phone #: ###-#### Inspection requested via web by Terry Scott
GC said hood ws not in place. Re-scheduled for next day in the morning
ELE18-04676 Electrical Rough-In12/10/201812/10/201812/10/2018 2:33:59 PMPPASS
Phone #: ###-#### Inspection requested via web by Dan Rohl
Rough-in ok to cover
p/s u/g n ok 2 meters
ELE18-04586 Rough-In Permanent Service12/10/201812/10/201812/10/2018 2:20:04 PMPPASS
For Both sides of Duplex.

Thank you,

Darryn Phone #: ###-#### Inspection requested via web by Darryn Coburn
Rough-in for both units ok
p/s u/g n ok
ELE18-03725 Final12/10/201812/10/201812/10/2018 2:19:30 PMPPASS
Swimming pool/spa Phone #: ###-#### Inspection requested via web by Lars Johnson
Final ok
ELE18-04602 Final12/7/201812/10/201812/10/2018 10:28:59 AMAPASS
Natalie Wiklund

2083424039 Phone #: ###-#### Inspection requested via web by BRS Permitting
Solar Array final ok
ELE18-04514 Final12/3/201812/10/201812/10/2018 9:57:48 AMAPASS
Phone #: ###-#### Inspection requested via web by Rob Maes
Solar Array final ok
ELE18-03925 Electrical Rough-In12/7/201812/10/201812/10/2018 9:47:00 AMACANC
Phone #: ###-#### Inspection requested via web by Laurie Hoelscher
Needed Final
ELE18-03925 Final12/10/201812/10/201812/10/2018 9:46:50 AMPPASS
Phone #: ###-#### Inspection requested via web by Laurie Hoelscher
Sign final ok