Inspections for the day of: Monday, December 11, 2000.
Number of inspections: 4
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorRick Jackson
TitleFIRE INSPECTOR
Phone #794-1981
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
FIR00-00289 INSP-Supply line flush12/6/200012/11/200012/11/2000 12:00:00 AMPFAIL
Scheduled by a contractor via Hello! on 12/06/2000 at 09:46:19. Contact: ###-####. see r/i for this date 12/11/2000 4:17:43 PM
FIR00-00630 INSP-Sprinkler Rough-in/Hydro12/8/200012/11/200012/11/2000 12:00:00 AMPFAIL
Scheduled by a contractor via Hello! on 12/08/2000 at 09:31:17. Contact: ###-####./// hydro okay on attic system. need additional sway bracing; overspaced heads; painted heads; inspectors test not installed per plans and will relocate 12/12/2000 9:41:21 AM
FIR00-00663 INSP-Supply line flush12/8/200012/11/200012/11/2000 12:00:00 AMPPART
FIRE JEFF-- ###-#### SUPPLY LINE FLUSH///// not a flush - 6 inch main stubbed out for about 10 ft. They will complete at later date. 12/11/2000 4:14:47 PM
FIR00-00289 INSP-Sprinkler Rough-in/Hydro12/11/200012/11/200012/11/2000 12:00:00 AMPFAIL
Scheduled by Inspector: 409 On 12/11/2000 4:15:37 PM /// attempted to test the fire pumps - pumps rated at 3000 gpms; at flow of 3750 gpms the residual pressure was -1psi. TVFP is trying to figure out what is wrong. 12/11/2000 4:17:11 PM