BLD00-01483
| BLD-Foundation | 12/8/2000 | 12/11/2000 | 12/11/2000 12:00:00 AM | A | PART |
|
|
Scheduled by a contractor via Hello! on 12/08/2000 at 08:58:53. Contact: ###-####.
wip, ok w/ verbal corrections 12/11/2000 9:33:54 AM
|
BLD00-03172
| BLD-Framing/Rough-in | 12/8/2000 | 12/11/2000 | 12/11/2000 12:00:00 AM | A | PASS |
|
|
TONY-- ###-#### FR INSP CALL 1 HR BEFORE INSP
ok to insulate 12/11/2000 9:34:52 AM
|
BLD00-00665
| BLD-Final | 12/9/2000 | 12/11/2000 | 12/11/2000 12:00:00 AM | A | PART |
|
|
Scheduled by a contractor via Hello! on 12/09/2000 at 08:48:27. Contact: ###-####.
need to finish all the way, temp ok 12/11/2000 3:50:30 PM
|
BLD00-00668
| BLD-Final | 12/9/2000 | 12/11/2000 | 12/11/2000 12:00:00 AM | A | PART |
|
|
Scheduled by a contractor via Hello! on 12/09/2000 at 08:50:27. Contact: ###-####.
tepm occ. ok,, need to finish 12/11/2000 3:51:05 PM
|
BLD00-00669
| BLD-Final | 12/9/2000 | 12/11/2000 | 12/11/2000 12:00:00 AM | A | PART |
|
|
Scheduled by a contractor via Hello! on 12/09/2000 at 08:51:23. Contact: ###-####.
temp. occ. ok, need to finish all the way 12/11/2000 3:51:45 PM
|
MEC00-04032
| Rough-in | 12/9/2000 | 12/11/2000 | 12/11/2000 12:00:00 AM | P | CANC |
|
|
Scheduled by a contractor via Hello! on 12/09/2000 at 09:22:11. Contact: ###-####. Disp set to [CANC] by a contractor via Hello! on 12/11/2000 at 07:50:29.
|
MEC00-04032
| Pressure Test | 12/9/2000 | 12/11/2000 | 12/11/2000 12:00:00 AM | P | CANC |
|
|
Scheduled by a contractor via Hello! on 12/09/2000 at 09:22:29. Contact: ###-####. Disp set to [CANC] by a contractor via Hello! on 12/11/2000 at 07:51:03.
|
BLD00-03357
| BLD-Foundation | 12/11/2000 | 12/11/2000 | 12/11/2000 12:00:00 AM | P | PART |
|
|
Scheduled by a contractor via Hello! on 12/11/2000 at 07:25:29. Contact: ###-####.
already poured 12/11/2000 4:05:21 PM
|
BLD00-02916
| BLD-Framing/Rough-in | 12/11/2000 | 12/11/2000 | 12/11/2000 12:00:00 AM | P | PART |
|
|
framing and shear on garage Steve ###-####
shear only,,,ok---need elec. rouph 12/11/2000 1:55:12 PM
|
BLD00-02861
| BLD-Framing/Rough-in | 12/11/2000 | 12/11/2000 | 12/11/2000 12:00:00 AM | P | FAIL |
|
|
shear Mark ###-####
c/n on shear nailing and hold downs 12/11/2000 2:43:36 PM
|
BLD00-03033
| BLD-Foundation | 12/11/2000 | 12/11/2000 | 12/11/2000 12:00:00 AM | P | PART |
|
|
foundation wall Ryan ###-####
|
BLD00-02948
| BLD-Footing | 12/11/2000 | 12/11/2000 | 12/11/2000 12:00:00 AM | P | PART |
|
|
###-####
|
BLD00-00665
| BLD-Energy code compliance | 12/7/2000 | 12/11/2000 | 12/11/2000 12:00:00 AM | P | PASS |
|
|
Scheduled by a contractor via Hello! on 12/07/2000 at 11:25:29. Contact: ###-####.
12/11/2000 3:52:05 PM
|
BLD00-02485
| BLD-Final | 12/7/2000 | 12/11/2000 | 12/11/2000 12:00:00 AM | P | NH |
|
|
Scheduled by a contractor via Hello! on 12/07/2000 at 12:21:31. Contact: ###-####.
no inspection made but verify elec., s.d. , and address posting 12/11/2000 2:16:14 PM
|