BLD01-01228
| BLD-Aging Inspection | 12/11/2001 | 12/11/2001 | 12/18/2001 12:00:00 AM | | NR |
|
|
parking lot, need all other ok's....in front of st lukes... 12/18/2001 11:43:13 AM
|
BLD01-01449
| BLD-Aging Inspection | 12/11/2001 | 12/11/2001 | 12/17/2001 12:00:00 AM | | NR |
|
|
called Josh, says P&Z has signed...take card to office asap 12/17/2001 3:10:33 PM
|
BLD01-01260
| BLD-Aging Inspection | 12/11/2001 | 12/11/2001 | 12/13/2001 12:00:00 AM | | NR |
|
|
will need a visit...unable to contact at this time. 12/13/2001 9:21:29 AM
|
MIS01-00086
| MIS-Aging Inspection | 12/11/2001 | 12/11/2001 | 12/11/2001 12:00:00 AM | | NR |
|
|
grading, need pub. wks (Brian Murphey) ok for final...chk w/ project A. Morrison Park Apts. 12/11/2001 2:17:05 PM
|
BLD01-01859
| BLD-Aging Inspection | 12/11/2001 | 12/11/2001 | 12/11/2001 12:00:00 AM | | NR |
|
|
roof, exp 1-7-02 12/11/2001 2:17:48 PM
|
BLD01-01237
| BLD-Aging Inspection | 12/11/2001 | 12/11/2001 | 12/11/2001 12:00:00 AM | | PASS |
|
|
exp 12/11/2001 2:13:17 PM
|
BLD01-03160
| BLD-Conference | 12/11/2001 | 12/11/2001 | 12/11/2001 12:00:00 AM | A | PART |
|
|
Added by Inspector: 340 On 12/11/2001 11:49:12 AM w/ owner, may need site visit re light-ventilation for int room
|
BLD98-03705
| BLD-Foundation | 12/11/2001 | 12/11/2001 | 12/11/2001 12:00:00 AM | A | PART |
|
|
Added by Inspector: 340 On 12/11/2001 12:02:41 PM observed 12th (of 30) caisson pour...met w/ Chris Schiappa & Mike Spiker of MTI onsite....Mike recommends coring caissons at SW corner for add'l test; Chris states soil bearing numbers are ok...there is a clay layer that will impact mat bearing, contractor has been informed. Contractor is using pump/tremmie to displace ground water. Eng'r to address soil depth/ protection of Eastman garage ftgs...grade beam is partially exposed
|
BLD01-02093
| BLD-Final | 12/10/2001 | 12/11/2001 | 12/11/2001 12:00:00 AM | A | PASS |
|
|
Scheduled by a contractor via Hello! on 12/10/2001 at 15:22:44. Contact: ###-####.
|
BLD00-01649
| BLD-Framing/Rough-in | 12/10/2001 | 12/11/2001 | 12/11/2001 12:00:00 AM | A | PART |
|
|
MEL ###-#### need chk sf dampers at elev lobbies, wip 12/11/2001 6:26:42 PM
|
BLD00-03538
| BLD-Conference | 12/11/2001 | 12/11/2001 | 12/11/2001 12:00:00 AM | A | PART |
|
|
Added by Inspector: 340 On 12/11/2001 9:44:03 AM w/ John R.(?) arch w/ CHSQA re occ sep...1hr sep preferred/ req'd w/ shell as office tenant(McAlvaine) wants temp occ...
|
BLD00-03538
| BLD-Framing/Rough-in | 12/11/2001 | 12/11/2001 | 12/11/2001 12:00:00 AM | P | PART |
|
|
Scheduled by a contractor via Hello! on 12/11/2001 at 09:40:36. Contact: ###-####...wip, need wrap beams at upper level, ok to infill deck, seal shafts 12/11/2001 6:24:17 PM
|
BLD01-00596
| BLD-Framing/Rough-in | 12/11/2001 | 12/11/2001 | 12/11/2001 12:00:00 AM | P | FAIL |
|
|
Scheduled by a contractor via Hello! on 12/11/2001 at 10:30:24. Contact: ###-####....c/n, show revised eng'g for 1st fl. shear, air seal, cripples over hdrs, hvac ok? 12/11/2001 4:19:58 PM
|
BLD01-01635
| BLD-Conference | 12/11/2001 | 12/11/2001 | 12/11/2001 12:00:00 AM | P | PASS |
|
|
###-#### w/ owner re duplex req's for elec service...one only. 12/11/2001 3:17:27 PM
|
BLD01-00604
| BLD-Framing/Rough-in | 12/11/2001 | 12/11/2001 | 12/11/2001 12:00:00 AM | P | FAIL |
|
|
Scheduled by a contractor via Hello! on 12/11/2001 at 11:05:34. Contact: . c/n, see bld01-00594 12/11/2001 4:21:20 PM
|
BLD01-03160
| BLD-Conference | 12/10/2001 | 12/11/2001 | 12/11/2001 12:00:00 AM | P | PASS |
|
|
###-#### w/owner...lite ok if passage to expanded bedrom is as shown, approx. 1/2 open at common wall, min 12 s.f. per room dimension. 12/11/2001 3:09:20 PM
|
BLD01-02149
| BLD-Framing/Rough-in | 12/10/2001 | 12/11/2001 | 12/11/2001 12:00:00 AM | P | PART |
|
|
###-#### gary...ok to insul throughout...still need hvac r/i ok. 12/11/2001 9:40:48 AM
|