Inspections for the day of: Wednesday, December 11, 2002.
Number of inspections: 18
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorTony Young
TitleBLD-COM/RES INSPECTOR
Phone #794-9462
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
BLD01-00066 BLD-Aging Inspection12/11/200212/11/200212/11/2002 12:00:00 AM PASS
ok now for perm. occ 12/18/2002 7:59:32 AM
BLD00-01498 BLD-Aging Inspection12/11/200212/11/200212/11/2002 12:00:00 AM PASS
BLD00-02083 BLD-Aging Inspection12/11/200212/11/200212/11/2002 12:00:00 AM PASS
BLD00-03204 BLD-Aging Inspection12/11/200212/11/200212/11/2002 12:00:00 AM PASS
still working on 12/18/2002 8:03:34 AM
BLD02-02776 BLD-Foundation12/10/200212/11/200212/11/2002 12:00:00 AMAPART
clay--found wall; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie
BLD02-02775 BLD-Foundation12/10/200212/11/200212/11/2002 12:00:00 AMAPART
clay--found wall; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie
BLD02-02383 BLD-Other12/10/200212/11/200212/11/2002 12:00:00 AMAPART
Phone #: ###-#### Internet Inspection Request from: Rita DeYoungfirewall section 12/12/2002 9:57:43 AM
BLD02-02382 BLD-Other12/10/200212/11/200212/11/2002 12:00:00 AMAPART
Phone #: ###-#### Internet Inspection Request from: Rita DeYoungfire wall section 12/12/2002 9:57:28 AM
BLD02-02864 BLD-Footing12/10/200212/11/200212/11/2002 12:00:00 AMAPART
no approved plans on site, wip, looks ok so far w/ raising grade mark 12/12/2002 9:56:41 AM
BLD01-02054 BLD-Conference12/10/200212/11/200212/11/2002 12:00:00 AMAPART
Scheduled by a contractor via Hello! on 12/10/2002 at 17:23:49. Contact: ###-####.conf. on stairs 12/12/2002 9:57:00 AM
MEC02-02925 Final12/10/200212/11/200212/11/2002 12:00:00 AMPPASS
Scheduled by a contractor via Hello! on 12/10/2002 at 14:02:07. Contact: ###-####.
MEC02-02927 Final12/10/200212/11/200212/11/2002 12:00:00 AMPPASS
Scheduled by a contractor via Hello! on 12/10/2002 at 14:02:38. Contact: ###-####.
BLD02-01466 BLD-Final12/11/200212/11/200212/11/2002 12:00:00 AMPPASS
brad; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie
BLD02-02330 BLD-Final12/11/200212/11/200212/11/2002 12:00:00 AMPFAIL
###-#### dean c/n posted 12/12/2002 10:14:52 AM
BLD01-02054 BLD-Conference12/11/200212/11/200212/11/2002 12:00:00 AMPDONE
###-####
BLD02-02174 BLD-Framing/Rough-in12/10/200212/11/200212/11/2002 12:00:00 AMPPART
Scheduled by a contractor via Hello! on 12/10/2002 at 13:10:12. Contact: ###-####.int. framing all units 12/12/2002 1:22:59 PM
MEC02-03577 Final12/10/200212/11/200212/11/2002 12:00:00 AMPPASS
call 1st before insp--mrs. luce--###-####
BLD02-02175 BLD-Framing/Rough-in12/10/200212/11/200212/11/2002 12:00:00 AMPPART
Scheduled by a contractor via Hello! on 12/10/2002 at 13:12:17. Contact: ###-####.int. frame ok 12/12/2002 10:06:18 AM