Inspections for the day of: Thursday, December 11, 2008.
Number of inspections: 10
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorForrest France
TitleFIRE INSPECTOR
Phone #794-1981
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
FIR08-00796 INSP-Sprinkler Rough-in/Hydro12/10/200812/11/200812/12/2008 6:14:00 PMAPART
Rough-in inspection passed, one missing hanger added while on site. Hydrostatic test failed due to pressure loss at the guage. Site notes per TF.
FIR08-00278 INSP-Final Inspection12/11/200812/11/200812/11/2008 6:14:36 PMPPASS
Fire alarm permit doc finaled.
FIR08-00512 INSP-Final Inspection12/11/200812/11/200812/11/2008 6:10:41 PMPPASS
Fire alarm permit doc finaled.
FIR08-00614 INSP-Final Inspection12/10/200812/11/200812/11/2008 6:08:43 PMPPASS
Fire sprinkler permit work passed final inspection, contractor to provide stock of spare sprinklers per NFPA 13 req. of the type installed.
FIR07-01042 INSP-Sprinkler Rough-in/Hydro12/10/200812/11/200812/11/2008 6:06:03 PMPPART
24 hr. air testing completed and passed for both dry systems.
FIR08-00703 INSP-Alarm Testing12/11/200812/11/200812/11/2008 6:02:27 PMPPASS
Fire alarm testing passed.
FIR08-00721 INSP-Final Inspection12/10/200812/11/200812/11/2008 12:55:28 PMAPASS
Fire sprinkler permit work passed field inspection, permit finaled. NOTE: contractor agreed to install head guards at two locations where sprinklers are below 7' AFF and subject to mechanical damage.
BLD08-02297 FIRE-Final Inspection12/10/200812/11/200812/11/2008 12:50:52 PMAPASS
Fire life safety completed satisfactory, noted three missing doors to be provided as agreed.
BLD08-02296 FIRE-Final Inspection12/10/200812/11/200812/11/2008 12:49:43 PMAPASS
Fire life safety inspection passed, suite numbers on site and to be posted prior to final as discussed.
FIR08-00018 INSP-Sprinkler Rough-in/Hydro12/10/200812/11/200812/11/2008 12:48:47 PMAFAIL
Rough-in inspection for cover at the 9th floor failed due to an overspaced pendent, one overspaced SW head, need an additonal hanger at one location, noted close proximity between some pendent heads and electrical junction boxes at the ceiling which may create an obstruction depending upon the fixture installed- see spacing requirements per NFPA 13R 6.8.1.5.3.2, also need to maintain min. distances from heat sources per 6.7.7.1.5.3. Marked locations on as-built plans, need stamped resubmittals prior to final cover approvals.