BLD15-00137
| FIRE-Final Inspection | 12/11/2015 | 12/11/2015 | 12/11/2015 4:21:09 PM | P | PART |
|
|
Fire sprinkler inspection complete, fire alarm inspection complete. Life fire safety inspection peformed, only item not in place for inspection is the emergency exit discharge light located in the west canopy, all other items inspected/passed, will final life fire safety when emergency egress light is installed/operational.
|
BLD15-02075
| FIRE-Final Inspection | 12/11/2015 | 12/11/2015 | 12/11/2015 4:15:53 PM | P | PASS |
|
|
No fire sprinklers, fire alarm inspection complete. Life fire safety inspection passed/complete. The northwest door of tenant space (kitchen/dishwasher area) has thumb-turn deadblot on door, instructed to the superintendant of jod that the thumb turn will need to be changed to double key assembly or removed, he instructed to me that the thumb-turn was keyed for construction access and that the thumb-turn will be removed at completion of project.
|
FIR15-00722
| INSP-Final Inspection | 12/11/2015 | 12/11/2015 | 12/11/2015 4:11:35 PM | P | PASS |
|
|
Final fire alarm inspection passed/complete
|
FIR15-00722
| INSP-Sprinkler Rough-in/Hydro | 12/9/2015 | 12/11/2015 | 12/11/2015 4:10:06 PM | A | CANC |
|
|
Inspection request for fire alarm final, canceling this inspection and correcting inspection request
|
FIR15-00601
| INSP-Final Inspection | 12/11/2015 | 12/11/2015 | 12/11/2015 3:48:13 PM | P | PASS |
|
|
All previously noted items repaired. Final fire sprinkler inspection passed/complete.
|
BLD15-03145
| FIRE-Final Inspection | 12/10/2015 | 12/11/2015 | 12/11/2015 2:03:48 PM | P | FAIL |
|
|
Exit signs/lights must be illimunated at all times under normal building power. Exit signs/lights also need to have an emergency power supply able to provide not less than 90 minutes of power. Emergency egress lighting needs to be installed on the second level, currently the only emergency lighting on the floor is in the restrooms.
|
FIR15-00843
| INSP-Sprinkler Rough-in/Hydro | 12/10/2015 | 12/11/2015 | 12/11/2015 8:38:11 AM | A | PASS |
|
|
Rough to cover inspection for tenant space passed/complete, approved for cover.
|
FIR14-00751
| INSP-Final Inspection | 12/10/2015 | 12/11/2015 | 12/10/2015 4:10:33 PM | P | CANC |
|
|
Bldg L Final and trip test Please call Raul 30 min prior ###-#### Phone #: ###-#### >> Inspection requested via web by Jacci Hunt Phone #: ###-#### >> Inspection requested via web by Jacci Hunt Inspection cancelled from web by: Jacci Hunt
|
FIR14-00751
| INSP-Final Inspection | 12/10/2015 | 12/11/2015 | 12/10/2015 4:08:18 PM | P | CANC |
|
|
Bldg L Final and trip test Please call Raul 30 min prior ###-#### Phone #: ###-#### >> Inspection requested via web by Jacci Hunt Inspection cancelled from web by: Jacci Hunt
|
FIR14-00071
| INSP-Final Inspection | 12/10/2015 | 12/11/2015 | 12/10/2015 4:08:16 PM | P | CANC |
|
|
Bldg L Final and trip test Please call Raul 30 min prior ###-#### Phone #: ###-#### >> Inspection requested via web by Jacci Hunt Inspection cancelled from web by: Jacci Hunt
|