Inspections for the day of: Tuesday, December 11, 2018.
Number of inspections: 12
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorJack Reynolds
TitleMEC INSPECTOR
Phone #208-803-2395
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
MEC18-03643 Pressure Test12/10/201812/11/201812/11/2018 3:58:50 PMPPASS
P/T IS FOR FLUE
INSTALLER DAVID ###-#### Phone #: ###-#### Inspection requested via web by Aaron Alandt
- 5lb flue pressure test ok
MEC18-05927 Pressure Test12/11/201812/11/201812/11/2018 3:29:38 PMPPASS
Sean is Journeyman that completed job. Homeowner will be home for access. Double valve/tee in crawl, pressure gauge in kitchen. Phone #: ###-#### Inspection requested via web by Scott Sparrell
- 20lb gas pressure test ok
- need to see a shut off valve at range and the gas line secured to the floor
MEC18-04683 Rough-in12/11/201812/11/201812/11/2018 3:06:13 PMPNR
PAR 2 FLOOOR Phone #: ###-#### Inspection requested via web by Oleg Chervak
- talked with montey and he said they are not finished and it wouldn't pass yet
- not ready
MEC18-05878 Final12/11/201812/11/201812/11/2018 3:05:11 PMPNH
Phone #: ###-#### Inspection requested via web by Mary LaFayette
- no access to home
MEC18-05924 Final12/10/201812/11/201812/11/2018 2:35:34 PMPFAIL
Please call Tony Hall 1 hour prior to arrival. should have furnace set around noon. ###-#### Phone #: ###-#### Inspection requested via web by kelly Martin
- need to add a/c to permit. When a/c gets added call for a reinspection- furnace ac coil co ok
MEC18-05763 Rough-in12/10/201812/11/201812/11/2018 2:03:09 PMPFAIL
units 1 and 2 Phone #: ###-#### Inspection requested via web by Gary Reeves
- exhaust fans need sealed both units
- north unit has an exhaust fan upstairs that needs finished
- combustion air for water heater in mech closet upstairs both units
- will need to see a 5lb flue pressure test on both furnaces at final
MEC18-05763 Pressure Test12/10/201812/11/201812/11/2018 2:00:09 PMPFAIL
units 1 and 2 Phone #: ###-#### Inspection requested via web by Gary Reeves
- south unit pressure test fail gauge was at zero
- north unit pressure test 20lb ok
MEC18-05283 Final12/11/201812/11/201812/11/2018 1:09:15 PMPPASS
Dylin Phone #: ###-####
- final ok
MEC18-02743 Rough-in12/10/201812/11/201812/11/2018 11:55:19 AMAFAIL
Joe Phone #: ###-####
- Man J. doesnt match whats installed
- Man J. needs basement layout added
- gas line in attic needs supported
- house has a gas leak inside somewhere
(called the gas company to inform them of gas leak) and was told that they would want to see a gas pressure test performed by the city
- lineset in attic needs supported
- condensate line outside needs supported
- drain pan below furnace in the attic needs a wet switch
-supply branches need balance dampers
- all bedrooms upstairs and downstairs need a transfer or ducted return
- home owner needs to add bathroom exhaust fans to his own permit
- all work needs to be performed by permit holder
MEC18-04671 Final12/10/201812/11/201812/11/2018 9:13:49 AMAPASS
access: 5674
Adam: ###-#### Phone #: ###-#### Inspection requested via web by Frank Marturello
- final ok
MEC12-02306 Mec-Aging Inspection12/11/201812/11/201812/11/2018 8:34:45 AM FAIL
no activities on this site and no phone call back
- will expire after 180 days
MIS18-00458 MEC-Conference12/10/201812/11/201812/11/2018 8:12:08 AMANH
- No access to building
- Any mechanical work being performed needs to be permited with the City of Boise
- left notice