Inspections for the day of: Tuesday, December 12, 2006.
Number of inspections: 12
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorBob Reichert
TitleELE-INSPECTOR
Phone #794-1923
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
ELE06-04155 Final12/12/200612/12/200612/12/2006 4:28:10 PMPFAIL
WE HAVE MADE OUR COORRECTIONS AND ARE READY FOR THE COMPLETION OF THE FINAL INSPECTION. ; Phone #: ###-#### Internet Inspection Request from: BRIAN KEITH called, added to exst corr notice, breaker blanks shall be put in panel spaces, mc and emt shall be strapped, Johnson controller is to be abandoned, still has duct over panels, so left corr notice on door to mech room.
ELE06-03550 Final12/12/200612/12/200612/12/2006 4:25:07 PMPFAIL
Jason; Phone #: ###-#### Internet Inspection Request from: Cathy Weisshaupt called, left corr notice, BCC address shall agree with BLD- supposed to be suite 260, ID mains to agree with panels, NEC 408.4 every circuit shall be clear, concise, evident, and identified for its specific purpose. Detail shall allow each circuit to be distinguished from others., 110.12(C) there shall be no damaged parts, panel doors shall operate correctly.
ELE06-03185 Final12/12/200612/12/200612/12/2006 3:34:07 PMPPASS
JOB COMPLETE FINAL INSPECTION KEY IS ABOVE METER. ; Phone #: ###-#### Internet Inspection Request from: BRIAN KEITH called contr to add conduit straps, ok to final
ELE06-02364 Conference12/12/200612/12/200612/12/2006 1:56:26 PMPDONE
Scheduled by a contractor via Hello! on 12/12/2006 at 7:21:44 AM. Contact: ###-####. talked about buck-boost xfmrs, application ok, physical install up to contractor
ELE06-04490 Permanent Service12/12/200612/12/200612/12/2006 12:09:02 PMPPASS
Service change.; Phone #: ###-#### Internet Inspection Request from: Kathy Briggs p/s u/g rec ok, owner needs to provide clear space about panel before final
ELE06-03939 Final12/11/200612/12/200612/12/2006 11:46:56 AMAPASS
Glenn; Phone #: ###-#### Internet Inspection Request from: Sherri Bennett ok to final
ELE06-03938 Final12/11/200612/12/200612/12/2006 10:16:29 AMAPASS
Glenn; Phone #: ###-#### Internet Inspection Request from: Sherri Bennett ok to final
ELE05-02003 Final12/11/200612/12/200612/12/2006 9:56:59 AMAPART
jarod - half the 1st floor guest rooms ; Phone #: ###-#### Internet Inspection Request from: Patricia Smith 1st fl clgs ok to cover anop, 1st floor rooms anop ok to final
ELE06-03829 Electrical Rough-In12/11/200612/12/200612/12/2006 9:31:53 AMAFAIL
Requesting inspection to cover ceiling for area North of main corridor.; Phone #: ###-#### Internet Inspection Request from: Dan Hardisty called, left corr notice, BCC no violations shall be retained, NEC 725.3 abandoned Cl 2,3 PLTC cables shall be removed, 300.4(C) cables or raceway type wiring methods shall be supported according to their applicable articles
ELE06-04510 Electrical Rough-In12/11/200612/12/200612/12/2006 8:56:28 AMACANC
zane ; Phone #: ###-#### Internet Inspection Request from: Patricia Smith wrong type request, see rip
ELE06-04510 Rough-In Permanent Service12/12/200612/12/200612/12/2006 8:53:23 AMAPASS
zane ; Phone #: ###-#### Internet Inspection Request from: Patricia Smith corr made, ric ok, p/s u/g n ok
ELE06-04477 Temporary Service12/11/200612/12/200612/12/2006 8:30:06 AMAPASS
Phone #: ###-#### Internet Inspection Request from: Lynn Solmon t/s u/g n ok