Inspections for the day of: Tuesday, December 12, 2017.
Number of inspections: 19
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorJim Sly
TitleBLD-COM/RES INSPECTOR
Phone #794-9465
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
BLD15-01131 BLD-Energy code compliance12/12/201712/12/201712/12/2017 5:04:50 PMPPASS
Ed Phone #: ###-####
BLD16-01596 BLD-Energy code compliance12/12/201712/12/201712/12/2017 5:04:29 PMPPASS
Ed Phone #: ###-####
BLD16-01597 BLD-Energy code compliance12/12/201712/12/201712/12/2017 5:04:10 PMPPASS
Ed Phone #: ###-####
BLD17-02996 BLD-Framing/Rough-in12/12/201712/12/201712/12/2017 5:03:49 PMPPASS
Saki-would like as late as possible Phone #: ###-####
BLD17-04232 BLD-Final12/11/201712/12/201712/12/2017 5:03:21 PMPNR
John Phone #: ###-####
BLD17-03946 BLD-Footing12/12/201712/12/201712/12/2017 2:23:54 PMPPASS
Ryan Phone #: ###-####
BLD17-03687 BLD-Framing/Rough-in12/12/201712/12/201712/12/2017 1:56:46 PMPPASS
Phone #: ###-#### Inspection requested via web by brian mcgaha
BLD17-01881 BLD-Final12/11/201712/12/201712/12/2017 1:41:55 PMAPASS
Phone #: ###-#### Inspection requested via web by Naida Khan
BLD17-01881 DOC - Permit Finaled12/12/201712/12/201712/12/2017 1:41:44 PMPPASS
BLD17-03190 BLD-Footing12/12/201712/12/201712/12/2017 1:41:27 PMPPEND
Steve Phone #: ###-####
No approved plan on site. Wants to pour lowest section.....( circle 1 on plan) approx 6 foot x 18 foot section approx 3 foot deep. Recommended that Architect or Engineer make a site visit and approve. The rebar in this section appears to match the "un-approved" plan. Pour at own risk.
BLD06-02324 BLD-Final12/12/201712/12/201712/12/2017 11:36:45 AMAPART
Final unit 101. Phone #: ###-#### Inspection requested via web by Bob Thornton
OK for Temp. OK for Perm Occ. when Shell Bldg is signed off.
Corrected unit number from 201 to 101 // C_P 12/15/17
BLD17-03901 DOC - Permit Finaled12/12/201712/12/201712/12/2017 10:34:26 AMPPASS
BLD17-02689 BLD-Framing/Rough-in12/11/201712/12/201712/12/2017 10:34:14 AMAPASS
Phone #: ###-#### Inspection requested via web by Bob Fink
BLD17-03516 BLD-Conference12/11/201712/12/201712/12/2017 10:33:59 AMADONE
btwn 8-10 // Duke Phone #: ###-####
BLD17-02581 BLD-Final12/11/201712/12/201712/12/2017 10:13:13 AMAPASS
Call for access - Chris Phone #: ###-####
BLD17-02581 DOC - Permit Finaled12/12/201712/12/201712/12/2017 10:12:32 AMPPASS
BLD17-03534 BLD-Framing/Rough-in12/11/201712/12/201712/12/2017 9:45:09 AMANR
Phone #: ###-#### Inspection requested via web by Don Steinke
BLD17-02499 BLD-Final12/11/201712/12/201712/12/2017 9:44:50 AMAPASS
Long Do Phone #: ###-####
OK for Perm Occ.
BLD17-02503 BLD-Energy code compliance12/11/201712/12/201712/12/2017 9:13:34 AMAPASS
Phone #: ###-#### Inspection requested via web by Matthew Eberhard