Inspections for the day of: Wednesday, December 12, 2018.
Number of inspections: 11
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorTroy Cobbley
TitleFIRE INSPECTOR
Phone #794-9483
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
FIR18-00428 INSP-Final Inspection12/11/201812/12/201812/12/2018 3:11:22 PMAFAIL
Need all ceiling tile installed prior to a final for the 3rd floor.

Tony Cetani is the contact. Phone #: ###-#### Inspection requested via web by Stan Beus
BLD18-02834 FIRE-Final Inspection12/12/201812/12/201812/12/2018 2:33:51 PMPFAIL
Life safety will be ok to pass when I'm directed by the Building Dept/Fire Dept. that an acceptable agreement has been reached on the fire sprinkler system.
FIR18-00879 INSP-Final Inspection12/12/201812/12/201812/12/2018 2:32:48 PMPPASS
Permit finaled
FIR18-00776 INSP-Supply line flush12/11/201812/12/201812/12/2018 1:54:09 PMPPASS
Underground flush passed. Flow was not as expected so Suez is going to follow up that the flow is as provided for design.

Set up for 1:00 pm Phone #: ###-#### Inspection requested via web by Sam Ball
FIR18-00775 INSP-Supply line flush12/11/201812/12/201812/12/2018 1:53:33 PMPPASS
Underground flush passed. Flow was not as expected so Suez is going to follow up that the flow is as provided for design.

Set up for 1:00 pm Phone #: ###-#### Inspection requested via web by Sam Ball
BLD18-03617 FIRE-Final Inspection12/12/201812/12/201812/12/2018 1:27:04 PMPPASS
Life safety passed. Matt to install lever hardware on the east side door as per plan prior to a building inspection.


Matt Phone #: ###-####
BLD18-04295 FIRE-Final Inspection12/11/201812/12/201812/12/2018 12:06:35 PMPPASS
Life safety passed



Keith Phone #: ###-####
BLD18-03509 FIRE-Final Inspection12/12/201812/12/201812/12/2018 11:45:40 AMPPASS
life safety passed

Call half hour before to meet // Tim Phone #: ###-####
FIR18-00903 INSP-Final Inspection12/11/201812/12/201812/12/2018 10:53:10 AMAFAIL
Scope of work is complete but permit can not be finaled until the fire sprinkler system monitoring system has been installed and tested.

Adam Phone #: ###-####
FIR18-00583 INSP-Sprinkler Rough-in12/11/201812/12/201812/12/2018 9:28:15 AMAFAIL
This inspection was for the Area "C" Fitness Center. Piping could not be viewed due to insulation blocking it. Could not perform inspection. No piping to be covered prior to a rough-in inspection.

Tony Cetani is the contact. Phone #: ###-#### Inspection requested via web by Stan Beus
FIR18-00708 INSP-Sprinkler Rough-in12/11/201812/12/201812/12/2018 9:26:54 AMAPASS
The piping above the hardlids in Area "C" Restrooms at the east side of the building is ok for cover.