Inspections for the day of: Thursday, December 12, 2019.
Number of inspections: 11
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorMark Moncarr
TitleELE-INSPECTOR
Phone #685-9023
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
ELE19-04233 Final12/12/201912/12/201912/12/2019 2:49:40 PMPPASS
Phone #: ###-#### Inspection requested via web by Jim Williams Ok final
ELE19-04769 Electrical Rough-In12/12/201912/12/201912/12/2019 1:18:15 PMPPASS
Partial cover Phone #: ###-#### Inspection requested via web by Greg Idsinga Ok cover entry ceiling, back wall living, bed and bath at front of house.
ELE19-04760 Final12/11/201912/12/201912/12/2019 12:23:28 PMPPASS
Heat trace connections. Phone #: ###-#### Inspection requested via web by Kevin Perez Ok final heat trace for N outside stairwell. 1-20a 2 pole and 30a 2 pole GFPE brkrs installed. Function properly
ELE19-04531 Permanent Service12/10/201912/12/201912/12/2019 10:47:58 AMAPASS
new electrical service Phone #: ###-#### Inspection requested via web by Deb Morton p/s u/g n ok
ELE19-04503 Electrical Rough-In12/11/201912/12/201912/12/2019 10:27:43 AMAPASS
ug conduit building interior Phone #: ###-#### Inspection requested via web by Lee VanSchoiack Ok cover ground work SE side
ELE19-04494 Electrical Rough-In12/11/201912/12/201912/12/2019 9:50:50 AMAPASS
Thank you. Phone #: ###-#### Inspection requested via web by CHRIS CARMINE Ok cover ceiling
ELE19-04401 Permanent Service12/11/201912/12/201912/12/2019 9:11:31 AMAPASS
Phone #: ###-#### Inspection requested via web by Dean Gernaat service on garage. p/s o/h n ok
ELE19-04531 Electrical Rough-In12/10/201912/12/201912/12/2019 8:37:28 AMAPASS
partial walls Phone #: ###-#### Inspection requested via web by Deb Morton Ok cover from center to N side.
ELE16-00796 ELE-Aging Inspection12/12/201912/12/201912/12/2019 6:11:48 AM DONE
Spoke to contractor on 12/11, he said he would look into it.
ELE16-00717 ELE-Aging Inspection12/12/201912/12/201912/12/2019 6:00:43 AM PASS
Ok final. Main brkr moved to oppostie side to give working clearence per code.
ELE16-00717 Final12/12/201912/12/201912/12/2019 5:59:47 AMAPASS
Ok final. Main brkr relocated to opposite side of generator which gives proper working clearence.