ESC04-01138
| BMP Violation | 12/10/2004 | 12/13/2004 | 12/13/2004 12:00:00 AM | A | PART |
|
|
Follow up: Refer to notes under ESC04-00011 on today's date. 12/13/2004 4:00:15 PM
|
ESC04-00011
| BMP Violation | 12/10/2004 | 12/13/2004 | 12/13/2004 12:00:00 AM | A | PART |
|
|
Follow up: Lifted stop work: Contractor was informed that additional bmp's needed on a couple of areas of bare slopes and to continue to implement provisions which would prevent erosion/sedimentation from occurring. Also, to observe project area and if additional trouble areas are noticed to take action. The lower basin next to Warm Springs is now being used as a construction sediment basin. This should continue until all construction is completed during the sub-division stage and structure building stage. No discharge is allowed until final provisions are in place, (slopes in basin and on all bare areas) and construction is completed and only then upon meeting water quality standards. Updated EPA of conditions on site and that the stop work is lifted. Will follow up. 12/13/2004 3:58:48 PM
|
ESC04-00011
| BMP Violation | 12/10/2004 | 12/13/2004 | 12/13/2004 12:00:00 AM | P | CANC |
|
|
|
ESC04-00011
| Conference | 12/12/2004 | 12/13/2004 | 12/13/2004 12:00:00 AM | P | DONE |
|
|
Inspection requested by RP, meet 1:30. Refer to notes outlined under ESC04-00011 on today's date. 12/13/2004 3:59:50 PM
|
ESC04-01514
| Site Preparation | 12/9/2004 | 12/13/2004 | 12/13/2004 12:00:00 AM | P | PART |
|
|
Discussed projects with rp Todd-@ ###-####. Need to secure signs better, sweep streets and remove port-a-pot to behind sidewalk. Will follow up. 12/13/2004 4:01:49 PM
|