Inspections for the day of: Friday, December 13, 2013.
Number of inspections: 10
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorForrest France
TitleFIRE INSPECTOR
Phone #794-1981
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
FIR13-00233 INSP-Final Inspection12/12/201312/13/201312/18/2013 5:09:20 PMAPART
Jonothan Phone #: ###-####
FIR12-00681 INSP-Final Inspection12/12/201312/13/201312/13/2013 3:38:09 PMAPART
C/N items include matched temp heads at an electrical room, replace hanger on added coverage, access to NW elevator machine room, floor drain function at the fire pump room.
FIR13-00133 INSP-Final Inspection12/12/201312/13/201312/13/2013 3:34:32 PMAPART
C/N items on 16th floor and the penthouse level.
FIR13-00011 INSP-Final Inspection12/12/201312/13/201312/13/2013 3:33:21 PMAPART
Refer to fire plan review note # 2 regarding alternate agreement for trip times at the dry systems. C/N items noted at floors 7,8,9, and 12..
FIR12-00723 INSP-Final Inspection12/12/201312/13/201312/13/2013 3:30:39 PMAPART
Noted unfinished circulation, lobby and corridor areas.
FIR12-00721 INSP-Final Inspection12/12/201312/13/201312/13/2013 3:29:21 PMAPART
Incomplete ceilings, finishes and construction for shell work at the lobby and entry areas.
FIR12-00634 INSP-Final Inspection12/12/201312/13/201312/13/2013 3:27:14 PMAPART
Refer to fire plan review notes item # 7 regarding isolation valves. Also noted missing caps at several locations.
FIR13-00601 INSP-Final Inspection12/13/201312/13/201312/13/2013 9:11:31 AMPPASS
Fire alarm permit finaled.
FIR13-00601 INSP-Conference12/12/201312/13/201312/13/2013 9:10:54 AMADONE
Site inspection and functional testing completed.
FIR13-00661 INSP-Sprinkler Rough-in12/12/201312/13/201312/13/2013 9:08:42 AMAPART
Okay to cover overhead fire sprinkler work at the second floor grid ceiling areas per the project scope.