ELE12-01789
| ELE-Aging Inspection | 12/13/2016 | 12/13/2016 | 12/14/2016 12:36:38 PM | | DONE |
|
|
Left notice with new owner. He will try to get an in touch with the contractor
|
ELE12-01275
| ELE-Aging Inspection | 12/13/2016 | 12/13/2016 | 12/14/2016 10:37:37 AM | | DONE |
|
|
Called contractor, He will schedule final
|
ELE16-03908
| Rough-In Permanent Service | 12/13/2016 | 12/13/2016 | 12/13/2016 1:32:48 PM | P | PART |
|
|
not ready till after 11:00 am Phone #: ###-#### Inspection requested via web by Bob Glenn WUI Zone A requirements. No soffits. Interior only ok to cover p/s u/g n ok
|
ELE16-04010
| Final | 12/12/2016 | 12/13/2016 | 12/13/2016 12:38:04 PM | P | CANC |
|
|
Our goal is to have this done in the morning so we may not be on site. The temp pole will be next to the transformer feeding the gas station. The number listed is for Ben so please contact Ben if you have any problems or see violations. Thanks Phone #: ###-#### Inspection requested via web by Kelly Tarter Needed temp service
|
ELE16-04010
| Temporary Service | 12/13/2016 | 12/13/2016 | 12/13/2016 12:37:57 PM | P | PASS |
|
|
Our goal is to have this done in the morning so we may not be on site. The temp pole will be next to the transformer feeding the gas station. The number listed is for Ben so please contact Ben if you have any problems or see violations. Thanks Phone #: ###-#### Inspection requested via web by Kelly Tarter t/s u/g n ok
|
ELE16-03994
| Final | 12/12/2016 | 12/13/2016 | 12/13/2016 12:17:49 PM | P | PASS |
|
|
Phone #: ###-#### Inspection requested via web by Samatha Solberg Final ok
|
ELE16-03994
| Electrical Rough-In | 12/13/2016 | 12/13/2016 | 12/13/2016 12:17:33 PM | P | PASS |
|
|
Phone #: ###-#### Inspection requested via web by Samatha Solberg Rough in ok
|
ELE16-02202
| Final | 12/12/2016 | 12/13/2016 | 12/13/2016 11:31:37 AM | A | PASS |
|
|
Phone #: ###-#### Inspection requested via web by Greg Traudt Final ok
|
ELE16-03991
| Final | 12/12/2016 | 12/13/2016 | 12/13/2016 10:33:00 AM | A | PASS |
|
|
Job is accessable from the alley behind the house by lifting up the garage door. Replaced wire and outlet to garage door opener. Phone #: ###-#### Inspection requested via web by Jonathan Poot Rough in ok
|
ELE16-03991
| Electrical Rough-In | 12/13/2016 | 12/13/2016 | 12/13/2016 10:32:32 AM | P | CANC |
|
|
Job is accessable from the alley behind the house by lifting up the garage door. Replaced wire and outlet to garage door opener. Phone #: ###-#### Inspection requested via web by Jonathan Poot Rough in ok
|
ELE16-03242
| Final | 12/12/2016 | 12/13/2016 | 12/13/2016 10:23:59 AM | A | PASS |
|
|
Phone #: ###-#### Inspection requested via web by David Feller Final ok
|
ELE16-03242
| Electrical Rough-In | 12/13/2016 | 12/13/2016 | 12/13/2016 10:23:41 AM | P | PASS |
|
|
Phone #: ###-#### Inspection requested via web by David Feller Rough in ok
|
ELE16-00662
| Final | 12/12/2016 | 12/13/2016 | 12/13/2016 10:07:11 AM | A | PART |
|
|
Partial final, north office area, warehouse and site/exterior of building. Phone #: ###-#### Inspection requested via web by Debby Pierce Partial final North office and Wearhouse only Final ok
|