Inspections for the day of: Friday, December 14, 2007.
Number of inspections: 15
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorTroy Cobbley
TitleFIRE INSPECTOR
Phone #794-9483
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
FIR07-00949 INSP-Sprinkler Rough-in12/14/200712/14/200712/14/2007 4:48:46 PMPPASS
The underground sprinkler piping is ok to cover
FIR07-00634 INSP-Final Inspection12/13/200712/14/200712/14/2007 4:48:08 PMPCANC
The fire alarm systems ended up not being tested due to time constraints and tamper switch issues. Per Matt his plans show two tampers switches. Each sprinkler system actually has three existing valves that need monitored. The sprinkler contractor failed to install the floor control valves which is two additional tampers. A total of five tamper switches have not been installed. No testing has been performed. The phone line troubles showing the first part of the day have been repaired. As-builts will be required not resubmittals. An updated map will be required as well.
FIR07-00630 INSP-Final Inspection12/13/200712/14/200712/14/2007 4:47:35 PMPCANC
The fire alarm systems ended up not being tested due to time constraints and tamper switch issues. Per Matt his plans show two tampers switches. Each sprinkler system actually has three existing valves that need monitored. The sprinkler contractor failed to install the floor control valves which is two additional tampers. A total of five tamper switches have not been installed. No testing has been performed. The phone line troubles showing the first part of the day have been repaired. As-builts will be required not resubmittals. An updated map will be required as well.
FIR07-00633 INSP-Final Inspection12/13/200712/14/200712/14/2007 4:47:01 PMPCANC
The fire alarm systems ended up not being tested due to time constraints and tamper switch issues. Per Matt his plans show two tampers switches. Each sprinkler system actually has three existing valves that need monitored. The sprinkler contractor failed to install the floor control valves which is two additional tampers. A total of five tamper switches have not been installed. No testing has been performed. The phone line troubles showing the first part of the day have been repaired. As-builts will be required not resubmittals. An updated map will be required as well.
FIR07-00635 INSP-Final Inspection12/13/200712/14/200712/14/2007 4:46:39 PMPCANC
The fire alarm systems ended up not being tested due to time constraints and tamper switch issues. Per Matt his plans show two tampers switches. Each sprinkler system actually has three existing valves that need monitored. The sprinkler contractor failed to install the floor control valves which is two additional tampers. A total of five tamper switches have not been installed. No testing has been performed. The phone line troubles showing the first part of the day have been repaired. As-builts will be required not resubmittals. An updated map will be required as well.
FIR07-00632 INSP-Final Inspection12/13/200712/14/200712/14/2007 4:46:18 PMPCANC
The fire alarm systems ended up not being tested due to time constraints and tamper switch issues. Per Matt his plans show two tampers switches. Each sprinkler system actually has three existing valves that need monitored. The sprinkler contractor failed to install the floor control valves which is two additional tampers. A total of five tamper switches have not been installed. No testing has been performed. The phone line troubles showing the first part of the day have been repaired. As-builts will be required not resubmittals. An updated map will be required as well.
FIR07-00629 INSP-Final Inspection12/13/200712/14/200712/14/2007 4:45:56 PMPCANC
The fire alarm systems ended up not being tested due to time constraints and tamper switch issues. Per Matt his plans show two tampers switches. Each sprinkler system actually has three existing valves that need monitored. The sprinkler contractor failed to install the floor control valves which is two additional tampers. A total of five tamper switches have not been installed. No testing has been performed. The phone line troubles showing the first part of the day have been repaired. As-builts will be required not resubmittals. An updated map will be required as well.
FIR07-00631 INSP-Final Inspection12/13/200712/14/200712/14/2007 4:45:33 PMPCANC
The fire alarm systems ended up not being tested due to time constraints and tamper switch issues. Per Matt his plans show two tampers switches. Each sprinkler system actually has three existing valves that need monitored. The sprinkler contractor failed to install the floor control valves which is two additional tampers. A total of five tamper switches have not been installed. No testing has been performed. The phone line troubles showing the first part of the day have been repaired. As-builts will be required not resubmittals. An updated map will be required as well.
BLD07-00602 FIRE-Final Inspection12/14/200712/14/200712/14/2007 4:39:40 PMPFAIL
The project related fire sprinkler and fire alarm need to be finaled first. I let paul know that self closing doors are required. This was verified with Tim in plan review. A knox key box is being worked out as well.
BLD07-00606 FIRE-Final Inspection12/14/200712/14/200712/14/2007 4:38:59 PMPFAIL
The project related fire sprinkler and fire alarm need to be finaled first. I let paul know that self closing doors are required. This was verified with Tim in plan review. A knox key box is being worked out as well.
BLD07-00599 FIRE-Final Inspection12/14/200712/14/200712/14/2007 4:38:25 PMPFAIL
The project related fire sprinkler and fire alarm need to be finaled first. I let paul know that self closing doors are required. This was verified with Tim in plan review. A knox key box is being worked out as well.
FIR07-00637 INSP-Sprinkler Rough-in/Hydro12/13/200712/14/200712/14/2007 4:36:20 PMAPASS
The second floor hydro test passed. The second floor sprinkler piping is ok to cover. I spent an extended amount of time pointing out fire proofing that had not been repaired. There were also loose hanger rings. I stated again that resubmittals would be required.
BLD06-03377 FIRE-Final Inspection12/14/200712/14/200712/14/2007 11:57:05 AMPNR
Called Terry and told him we couldn't do the life safety until the sprinkler system has been finaled..KR
BLD07-03056 FIRE-Final Inspection12/13/200712/14/200712/14/2007 10:34:03 AMAPASS
life safety passed
BLD07-02535 FIRE-Final Inspection12/13/200712/14/200712/14/2007 9:47:03 AMAPASS
life safety passed