NAF15-00030
| INSP-Final | 12/13/2016 | 12/14/2016 | 12/14/2016 3:37:13 PM | P | PASS |
|
|
Fire Life Safety Pass. Verified emergency lights, fire extinguishers and unit smoke alarms.
|
NAF16-00077
| INSP-Final | 12/14/2016 | 12/14/2016 | 12/14/2016 3:32:42 PM | P | PASS |
|
|
System test completed satisfactory to include heat trace monitoring. Scope of work complete. Permit Finaled.
|
NAF15-00040
| INSP-Final | 12/13/2016 | 12/14/2016 | 12/14/2016 3:30:20 PM | P | PASS |
|
|
Scope of work complete. Permit finaled.
|
NAF16-00007
| INSP-Final | 12/13/2016 | 12/14/2016 | 12/14/2016 3:29:59 PM | P | PASS |
|
|
Systems test completed satisfactory. Scope of work complete. Permit finaled.
|
NAF16-00051
| INSP-Conference | 12/13/2016 | 12/14/2016 | 12/14/2016 1:23:52 PM | A | DONE |
|
|
Discussed with Rory and Jamie process for requesting temp occupancy of manufacturering side only. Discussed that all active fire protection systems and life safety items would need to be completed.
|
NAF16-00059
| INSP-Sprinkler Rough-in | 12/13/2016 | 12/14/2016 | 12/14/2016 1:22:47 PM | A | CANC |
|
|
No rough-in completed.
|
NAF16-00012
| INSP-Sprinkler Rough-in | 12/14/2016 | 12/14/2016 | 12/14/2016 12:00:00 AM | P | DONE |
|
|
At time of inspection tenting completed satisfactory. One uncovered spot identified, insulators on site to correct.
|