PLM99-03482
| Final | 12/14/1999 | 12/15/1999 | 12/15/1999 12:00:00 AM | A | PART |
|
|
Scheduled by a contractor via Hello! on 12/14/1999 at 13:01:36. Contact: ###-####. Elevate water heater and pan to prohibit condensate from entering pan.
|
PLM99-04091
| Final | 12/14/1999 | 12/15/1999 | 12/15/1999 12:00:00 AM | A | PASS |
|
|
Scheduled by a contractor via Hello! on 12/14/1999 at 13:32:29. Contact: ###-####. R/I, final ok.
|
PLM99-04114
| Water and/or Sewer | 12/14/1999 | 12/15/1999 | 12/15/1999 12:00:00 AM | A | FAIL |
|
|
Scheduled by a contractor via Hello! on 12/14/1999 at 14:19:09. Contact: ###-####. Incomplete.
|
PLM99-04115
| Water and/or Sewer | 12/14/1999 | 12/15/1999 | 12/15/1999 12:00:00 AM | A | FAIL |
|
|
Scheduled by a contractor via Hello! on 12/14/1999 at 14:21:21. Contact: ###-####. Incomplete.
|
PLM99-04116
| Water and/or Sewer | 12/14/1999 | 12/15/1999 | 12/15/1999 12:00:00 AM | A | FAIL |
|
|
Scheduled by a contractor via Hello! on 12/14/1999 at 14:22:28. Contact: ###-####. Incomplete.
|
PLM99-04117
| Water and/or Sewer | 12/14/1999 | 12/15/1999 | 12/15/1999 12:00:00 AM | A | FAIL |
|
|
Scheduled by a contractor via Hello! on 12/14/1999 at 14:23:42. Contact: ###-####. Incomplete.
|
PLM99-04125
| Sprinkler (Final) | 12/15/1999 | 12/15/1999 | 12/15/1999 12:00:00 AM | P | PASS |
|
|
###-####- darin Sprinkler final ok.
|
PLM99-03166
| Final | 12/15/1999 | 12/15/1999 | 12/15/1999 12:00:00 AM | P | PASS |
|
|
Scheduled by a contractor via Hello! on 12/15/1999 at 09:41:24. Contact: ###-####. Final ok.
|
PLM99-04130
| Plumbing Rough-in | 12/15/1999 | 12/15/1999 | 12/15/1999 12:00:00 AM | P | PART |
|
|
###-#### GARY Ok to cover inside walls, will change shower valve to thermal or pressure balance.
|
PLM99-03860
| Plumbing Rough-in | 12/15/1999 | 12/15/1999 | 12/15/1999 12:00:00 AM | P | FAIL |
|
|
Tests failed, use fittings to make offsets in CPUC, hang piping, use approved valves, braze all joints in compressed air systems.
|