Inspections for the day of: Tuesday, December 15, 2009.
Number of inspections: 7
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorForrest France
TitleFIRE INSPECTOR
Phone #794-1981
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
FIR09-00364 INSP-Sprinkler Rough-in12/14/200912/15/200912/15/2009 4:51:43 PMPFAIL
Inspection for overhead cover at the drop ceilings in the corridors and adjacent rooms failed due to some items including missing seismic bracing, one blocked upright, two areas missing coverage, one mixed head, one upright to be relocated- see plans for red-lines.
FIR09-00304 INSP-Final Inspection12/15/200912/15/200912/15/2009 4:47:56 PMPNR
Final pending noted corrections, satisfactory retest, and clear panel.
FIR09-00305 INSP-Final Inspection12/15/200912/15/200912/15/2009 4:44:38 PMPNR
Pending correction items and project related FIR permit work.
FIR09-00193 INSP-Final Inspection12/14/200912/15/200912/15/2009 4:42:29 PMPPASS
Corrections field verified, final inspection passed, fire alarm permit finaled.
FIR09-00282 INSP-Final Inspection12/11/200912/15/200912/15/2009 1:03:33 PMANR
Noted one SW head at the first floor mechanical closet in need of adjustment, provide "911" sign at the outside bell, project related FIR permits 09-00283 thru 286 are "ready to issue", need escutcheons installed and travel caps removed at units 518,520, and 524, noted heat has been provided and sheetrock ceilings in the shell unit are done, riser supervision to be tested in conjunction with fire alarm permit work re-inspect.
FIR09-00347 INSP-Sprinkler Rough-in/Hydro12/14/200912/15/200912/15/2009 12:53:57 PMAPART
Hydrostatic testing for the overhead system piping completed satisfactory, also okayed for cover heads in drop ceilings at the first floor.
FIR09-00257 INSP-Final Inspection12/11/200912/15/200912/15/2009 11:28:04 AMAPASS
Fire sprinkler permit final previously approved per activity notes dated 8/7/09 by T. Cobbley.