MEC99-04178
| Final | 12/15/1999 | 12/16/1999 | 12/16/1999 12:00:00 AM | A | PASS |
|
|
Scheduled by a contractor via Hello! on 12/15/1999 at 08:36:01. Contact: ###-####. Final ok.
|
MEC99-04122
| Final | 12/15/1999 | 12/16/1999 | 12/16/1999 12:00:00 AM | A | PASS |
|
|
Scheduled by a contractor via Hello! on 12/15/1999 at 13:12:00. Contact: ###-####. Final ok.
|
MEC99-03774
| Final | 12/16/1999 | 12/16/1999 | 12/16/1999 12:00:00 AM | P | PASS |
|
|
this was subposed to be done on the 15th not done yet, why? pat ###-#### Final ok.
|
MEC99-02727
| Final | 12/16/1999 | 12/16/1999 | 12/16/1999 12:00:00 AM | P | PASS |
|
|
Scheduled by a contractor via Hello! on 12/16/1999 at 10:09:45. Contact: ###-####. Final ok.
|
MEC99-04235
| Rough-in | 12/16/1999 | 12/16/1999 | 12/16/1999 12:00:00 AM | P | PASS |
|
|
nikki ###-#### R/I ok.
|
MEC99-04235
| Pressure Test | 12/16/1999 | 12/16/1999 | 12/16/1999 12:00:00 AM | P | PASS |
|
|
nikki###-#### Gas ok.
|