MIS03-00240
| FIR-Final | 12/15/2003 | 12/16/2003 | 12/16/2003 12:00:00 AM | A | FAIL |
|
|
repair the exit sign, provide lever hardware for th e south conference room exterior door, the fire alarm system does not meet current code. It is missing the manual pull station, smoke detector and horn in a normally occupied area. Contact Dave Miller for upgrade agreement. 12/16/2003 11:24:16 AM
|
BLD03-01059
| FIRE-Final Inspection | 12/16/2003 | 12/16/2003 | 12/16/2003 12:00:00 AM | P | CANC |
|
|
Contractor needed sprinkler roughin inspection. See FIR03-00450 and FIR03-00757 for comments 12/16/2003 3:56:24 PM
|
FIR03-00757
| INSP-Sprinkler Rough-in | 12/16/2003 | 12/16/2003 | 12/16/2003 12:00:00 AM | P | PART |
|
|
sprinkler piping is ok to cover
|
FIR03-00450
| INSP-Sprinkler Rough-in | 12/16/2003 | 12/16/2003 | 12/16/2003 12:00:00 AM | P | PART |
|
|
Pito test on the backflow preventer is OK. Alarm bell operates ok but I requested verification that the orfice matches the smallest sprinkler head orfice. Trapeze is ok on the main. Existing pipe sizing matches plans. Sprinkler pendants need to be changed to quick responce. Need signs on the riser, head wrench and NFPA 25. Still need alarm system completed. Need to double check review notes at final.
|
FIR03-00713
| INSP-Sprinkler Rough-in/Hydro | 12/11/2003 | 12/16/2003 | 12/16/2003 12:00:00 AM | P | PASS |
|
|
sprinkler piping is ok to cover 12/16/2003 12:37:12 PM
|
BLD03-01116
| FIRE-Final Inspection | 12/15/2003 | 12/16/2003 | 12/16/2003 12:00:00 AM | P | CANC |
|
|
I stopped by the job site and spoke with the male owner. I told him that I could not do a fire life safety inspection since the fire alarm plans had not been approved yet. He agreed and I left the project. Jenny called me later and asked if I could reschedule for tomorrow and do a life safety conference. I scheduled it for tomorrow. 12/16/2003 2:35:08 PM
|