BLD03-02377
| BLD-Grading Inspection | 12/12/2003 | 12/12/2003 | | | |
|
|
Footing subgrade approved by the geotechnical engineer
|
BLD03-01877
| BLD-Grading Inspection | 12/16/2003 | 12/16/2003 | 12/16/2003 12:00:00 AM | | PASS |
|
|
Final grading and drainage complete and approved.
|
BLD03-02010
| BLD-Grading Inspection | 12/16/2003 | 12/16/2003 | 12/16/2003 12:00:00 AM | | PASS |
|
|
Final grading and drainage complete and approved. Recommended to John Siekert that gutter chains be replaced with downspouts to more effectively convey the stormwater from the roof into the storm drain system to.
|
BLD03-02800
| BLD-Grading Inspection | 12/16/2003 | 12/16/2003 | 12/16/2003 12:00:00 AM | | PASS |
|
|
Footing subgrade has been approved by the geotechnical engineer.
|