Inspections for the day of: Monday, December 17, 2001.
Number of inspections: 10
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorJim Storey
TitleBLD-COM/RES INSPECTOR
Phone #794-9490
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
BLD01-02240 BLD-Footing12/14/200112/17/200112/17/2001 12:00:00 AMAPASS
###-#### ft ok mti report pending. 12/17/2001 9:27:10 AM
BLD01-01850 BLD-Final12/14/200112/17/200112/17/2001 12:00:00 AMAFAIL
TRAVIS ###-#### c/n posted 12/17/2001 10:48:28 AM
BLD01-01729 BLD-Framing/Rough-in12/14/200112/17/200112/17/2001 12:00:00 AMAPASS
Scheduled by a contractor via Hello! on 12/14/2001 at 13:17:39. Contact: .
BLD01-00039 BLD-Final12/14/200112/17/200112/17/2001 12:00:00 AMAPART
VERN ###-#### CELL ###-#### need mech final 12/17/2001 10:46:48 AM
BLD01-02743 BLD-Conference12/14/200112/17/200112/17/2001 12:00:00 AMAPASS
for conf-- justin ###-#### c/n on ft ok roof at front porch. 12/18/2001 9:40:03 AM
BLD01-02733 BLD-Footing12/17/200112/17/200112/17/2001 12:00:00 AMPPASS
###-#### ft ok 12/17/2001 4:50:53 PM
BLD01-02543 BLD-Framing/Rough-in12/17/200112/17/200112/17/2001 12:00:00 AMPPASS
Scheduled by a contractor via Hello! on 12/17/2001 at 11:22:06. Contact: ###-####.
BLD01-02401 BLD-Footing12/14/200112/17/200112/17/2001 12:00:00 AMPPASS
250-.3472 OR ###-#### CALL FIRST 15 TO 20 MIN. ft ok 12/17/2001 4:35:39 PM
MEC01-03671 Pressure Test12/5/200112/17/200112/15/2001 12:00:00 AMPCANC
Disp set to [CANC] by a contractor via Hello! on 12/15/2001 at 12:10:32.
MEC01-03671 Final12/14/200112/17/200112/15/2001 12:00:00 AMPCANC
Scheduled by a contractor via Hello! on 12/14/2001 at 15:02:26. Contact: ###-####. Disp set to [CANC] by a contractor via Hello! on 12/15/2001 at 12:11:09.