MIS01-00041
| MIS-Aging Inspection | 12/17/2001 | 12/17/2001 | 12/17/2001 12:00:00 AM | | PASS |
|
|
exp per terms of permit (9-01)....at charter school site? Rehab job.. 12/17/2001 11:41:21 AM 12/17/2001 11:42:19 AM 12/17/2001 11:43:06 AM
|
BLD01-02607
| BLD-Conference | 12/17/2001 | 12/17/2001 | 12/17/2001 12:00:00 AM | A | PASS |
|
|
Added by Inspector: 340 On 12/17/2001 9:20:24 AM rec'd eng's letter, ok. frame ok to continue
|
BLD00-03729
| BLD-Foundation | 12/14/2001 | 12/17/2001 | 12/17/2001 12:00:00 AM | A | PART |
|
|
bruce ###-####, masonry, pend MTI report. 12/17/2001 10:59:11 AM
|
BLD01-01643
| BLD-Final | 12/14/2001 | 12/17/2001 | 12/17/2001 12:00:00 AM | A | NR |
|
|
###-####.nr, need final for elev by elec. 12/17/2001 10:30:17 AM
|
BLD00-00153
| BLD-Final | 12/14/2001 | 12/17/2001 | 12/17/2001 12:00:00 AM | A | NR |
|
|
JIM ###-####; need plans, eng'g and signage per UBC std. recall 12/17/2001 11:12:10 AM
|
BLD01-01892
| BLD-Final | 12/14/2001 | 12/17/2001 | 12/17/2001 12:00:00 AM | A | FAIL |
|
|
Scheduled by a contractor via Hello! on 12/14/2001 at 21:57:36. Contact: ###-####...c/n, ext. steps,& handrail. 12/17/2001 10:29:41 AM
|
BLD01-02607
| BLD-Framing/Rough-in | 12/17/2001 | 12/17/2001 | 12/17/2001 12:00:00 AM | A | PART |
|
|
Added by Inspector: 340 On 12/17/2001 9:34:42 AM ok to cover int side for surface mount of elec.
|
BLD00-00081
| BLD-Conference | 12/17/2001 | 12/17/2001 | 12/17/2001 12:00:00 AM | A | PASS |
|
|
Added by Inspector: 340 On 12/17/2001 11:01:53 AM w/ CH2M hill eng'r...need final report/affidavit for seismic upgrade, Spec insp reports appear inadequate(failures,improper test methods); must show bldg up to specs.
|
BLD01-00228
| BLD-Conference | 12/17/2001 | 12/17/2001 | 12/17/2001 12:00:00 AM | A | PASS |
|
|
Added by Inspector: 340 On 12/17/2001 11:05:26 AM need eng's report for struct upgrade of entire portion of west wing.
|
BLD00-02394
| BLD-Conference | 12/17/2001 | 12/17/2001 | 12/17/2001 12:00:00 AM | A | PART |
|
|
Added by Inspector: 340 On 12/17/2001 11:15:35 AM w/ CH2M hill eng'r; need report/verification struct upgrade is up to spec, MTI reports appear inadequate...test methods for gunite/concrete to be followed per ACI, not schmidt-hammer test.
|
BLD01-02742
| BLD-Conference | 12/17/2001 | 12/17/2001 | 12/17/2001 12:00:00 AM | A | PASS |
|
|
Added by Inspector: 340 On 12/17/2001 11:40:38 AM rec'd photos of masonry infill bar...ok to install 2nd exit in fixed overhead door if all code items ok.
|
BLD01-01993
| BLD-Conference | 12/17/2001 | 12/17/2001 | 12/17/2001 12:00:00 AM | A | PASS |
|
|
Added by Inspector: 340 On 12/17/2001 12:05:11 PM re struct details; complete stairs, rails, etc...elev ok. w/ ph.1
|
BLD01-00539
| BLD-Conference | 12/17/2001 | 12/17/2001 | 12/17/2001 12:00:00 AM | P | PASS |
|
|
Added by Inspector: 340 On 12/17/2001 3:06:15 PM w/eng'r, need report for struct upgrade & appropriate testing.
|
BLD01-01449
| BLD-Conference | 12/17/2001 | 12/17/2001 | 12/17/2001 12:00:00 AM | P | PASS |
|
|
Added by Inspector: 340 On 12/17/2001 3:11:31 PM called cont...obtain final or turn in card as req'd; Josh said he'd take care of it.
|
BLD01-02607
| BLD-Conference | 12/17/2001 | 12/17/2001 | 12/17/2001 12:00:00 AM | P | PASS |
|
|
Scheduled by a contractor via Hello! on 12/17/2001 at 09:07:13. Contact: ###-####. w/ mgr onsite...need hvac install & approval. 12/17/2001 2:59:48 PM
|
BLD98-03705
| BLD-Foundation | 12/17/2001 | 12/17/2001 | 12/17/2001 12:00:00 AM | P | PART |
|
|
Scheduled by a contractor via Hello! on 12/17/2001 at 09:57:44. Contact: .caissons pending report; rec'd initial MTI conc. report...exceeds 5100psi at 7 days, 4000 psi req'd 12/17/2001 5:35:41 PM
|
BLD00-01649
| BLD-Framing/Rough-in | 12/17/2001 | 12/17/2001 | 12/17/2001 12:00:00 AM | P | PART |
|
|
###-#### c/n issued re ramps, guards, etc 12/17/2001 5:36:27 PM
|