ESC15-00771
| Aging Inspection | 12/18/2015 | 12/18/2015 | 12/22/2015 10:10:58 AM | | CANC |
|
|
|
ESC15-01482
| Site Preparation | 12/18/2015 | 12/18/2015 | 12/18/2015 4:51:15 PM | P | PASS |
|
|
|
ESC15-00729
| General Inspection | 12/18/2015 | 12/18/2015 | 12/18/2015 4:41:43 PM | P | FAIL |
|
|
Inspected area of work on Council Springs Creek where culvert for fire access road creek crossing is being installed. No construction activity occuring at time of inspection, site shut down due to wet conditions.
-Observed turbid water flowing in the creek channel approximately 1/4 mile below construction. Water seems to filter out in the biofiltration drainage area and culvert before flowing though Harris Ranch sub. Flow above construction is area is not clear but significantly less turbid than passing through construction area, indicating lack of BMPs or failure.
- The silt fence installed across the stream channel meant to retain and filter water is uprooted and turbid water is flowing downstream. Improper use of silt fence BMP. Checkdam with filter fabric should be utilized in combination with the existing SF - removing now will cause trapped silt to pass downstream.
-Another source of sediment is from the runoff coming down graded hillside and access road is flowing into creek water holding area (damned by silt fence mentioned above) and mixing with the stream flow. There are no BMPs to capture or slow this runoff into the creek holding pond. Positives: Above stream the coffer dam and stream diversion are working well and water coming out the pipe into the muddy holding pond is relatively clear. Along the creek banks where the road is being widened sediment control BMPs and stream bank buffer are effective and not damaged.
Correction: - Install wattles, silt fence, and rock check dams around area of work to complete. Consider diversion of runoff from the road and graded area with a berm and directiong it down the road instead of into creek.
RP Chad and Syman supervisor Andy were notified. Crews were sent to site to begin work. Rock will be ordered and checkdams installed ASAP but probably not today.
Snowmelt runoff and forecasted wet conditions make this an immediate priority.
|
ESC15-00721
| General Inspection | 12/18/2015 | 12/18/2015 | 12/18/2015 3:52:15 PM | | PASS |
|
|
|
ESC15-01283
| Tracking Control | 12/18/2015 | 12/18/2015 | 12/18/2015 3:44:21 PM | P | FAIL |
|
|
significant trackout, no site prep inspection, minimal BMPs
|
ESC15-00260
| General Inspection | 12/18/2015 | 12/18/2015 | 12/18/2015 3:04:07 PM | | CANC |
|
|
rescheduled for site final
|
ESC15-00852
| Aging Inspection | 12/18/2015 | 12/18/2015 | 12/18/2015 2:35:57 PM | | PASS |
|
|
Demo complete. ESC permit conditions satisfied. All permits finaled.
|
ESC15-00852
| DOC - Permit Finaled | 12/18/2015 | 12/18/2015 | 12/18/2015 2:35:30 PM | P | PASS |
|
|
|
ESC15-00733
| General Inspection | 12/18/2015 | 12/18/2015 | 12/18/2015 2:26:55 PM | | PASS |
|
|
WIP. Minimal exterior disturbance. No prohibited discharges observed.
|
ESC15-00732
| General Inspection | 12/18/2015 | 12/18/2015 | 12/18/2015 2:24:33 PM | | PASS |
|
|
WIP. Minimal exterior disturbance. No prohibited discharges observed.
|
ESC15-00477
| General Inspection | 12/18/2015 | 12/18/2015 | 12/18/2015 2:09:24 PM | | PASS |
|
|
Home construction complete. Site is landscaped and stabilized currently and a hillside bond has been issued to guarantee hillside stabilzation. Street and sidewalk have been cleaned, no loose dirt or materials on site.
Temp BMP DI bag shall stay installed during construction of adjacent home. Approved.
|
ESC15-00477
| DOC - Permit Finaled | 12/18/2015 | 12/18/2015 | 12/18/2015 2:07:59 PM | P | PASS |
|
|
|
ESC15-01061
| Tracking Control | 12/16/2015 | 12/18/2015 | 12/18/2015 2:05:33 PM | P | PASS |
|
|
Street and sidewalk were swept as requested. DI bag is installed and capturing sediment and filtering runoff.
No activity in mud. Silt fence installed is trenched properly and damaged sections removed. Approved.
|
ESC14-00886
| General Inspection | 12/17/2015 | 12/18/2015 | 12/18/2015 1:59:28 PM | A | PASS |
|
|
No trackout from site due to rock entrance, permit sign posted, and clearing limits are well observed. Additional wattles were installed to treat/slow runoff from within site to the left of the access drive as requested during site prep. No corrections at this time. WIP.
|
ESC15-00852
| DOC - Permit Finaled | 12/18/2015 | 12/18/2015 | 12/18/2015 12:57:21 PM | P | PASS |
|
|
|
ESC15-00985
| General Inspection | 12/18/2015 | 12/18/2015 | 12/18/2015 11:00:29 AM | A | PASS |
|
|
WIP. No prohibited discharges or trackout observed. See also ESC15-00934 for coverage on Payette Brewing Co. project.
|
ESC15-00934
| General Inspection | 12/18/2015 | 12/18/2015 | 12/18/2015 11:00:02 AM | P | PASS |
|
|
WIP. No prohibited discharges or trackout observed. See also ESC15-00985 for coverage on Payette Brewing Co. project.
|
ESC15-01068
| Complaint Inspection | 12/18/2015 | 12/18/2015 | 12/18/2015 10:58:01 AM | A | FAIL |
|
|
Complaint of muddy site received by Code Enforcement hotline...
Inspection observations: - Flat infill lot, 4 SFHs same builder - Concrete just poured probably yesterday. Excavated dirt for backfill is next to sidewalk. Very wet mud, some runoff and clods on sidewalk going to gutter. - Looks like concrete truck or pump crane leaked some fuel and there is a sheen on roadway and runoff.. - Receiving DI is 1 block to the west on Palouse and Hervey. No DI bag installed. - Permit signs are posted.
Corrections: - sweep sidewalk, provide stockpile buffer strip so no soil is on sidewalk. Install wattle as necessary - put spill absorbant on spill in road in front of project
Verbal CN issued to RP-GC Aaron Mcgee
RP stated he will be onsite with spill absorbant and broom ASAP this afternoon and will check in
|
ESC15-01285
| General Inspection | 12/18/2015 | 12/18/2015 | 12/18/2015 10:42:18 AM | A | PASS |
|
|
WIP on bricklaying for path. No uncontained stockpiles or materials. No muddy runoff. Section between Greenbelt and parking lot is complete. Parking lot storm drain receiving runoff from surrounding paved areas has inlet protection. No corrections issued at this time.
|
ESC15-00942
| General Inspection | 12/18/2015 | 12/18/2015 | 12/18/2015 9:56:53 AM | P | PASS |
|
|
WIP on vertical construction at River Street Storage. Site perimeter is surrounded by structural sediment barriers in the form of curbing and sidewalk(some new some existing). Disturbed area surrounded by security fence to control access. Staging area is being shared in parking lot of Pioneer where Payette Brewing project is underway.
No trackout. No muddy discharges. MS4 on River and 13th has sediment filter bag. Yellow permit sign posted. Site is well kept. No corrections at this time.
|
ESC15-00731
| General Inspection | 12/18/2015 | 12/18/2015 | 12/18/2015 8:51:50 AM | | PASS |
|
|
|
ESC14-00886
| Site Preparation | 12/17/2015 | 12/18/2015 | 12/17/2015 3:52:42 PM | P | CANC |
|
|
|