BLD17-03747
| Extend Permit 90/180 days | | 12/18/2018 | 12/18/2018 12:00:00 AM | | DONE |
|
|
request by email
: AT&T’s RRH manufacturer was unable to keep up with the projected delivery schedule, which delayed our build plan. The decision was therefore made to go ahead and build the project
covered by the 17-03737 BP along with the project that is covered by the BLD18-01827 permit (which is valid until 6/19/19).
Please do not hesitate to let me know if there is any additional information you require in order to grant the extension.
Greatly appreciate your time and assistance.
Kind regards,
Anne
Anne Catanach
Re-Entitlements
AT&T Mobility – Rocky Mountain Region
###-#### (Mobile)
ac8106@att.com
|
BLD17-03927
| Extend Permit 90/180 days | | 12/18/2018 | 12/18/2018 12:00:00 AM | | DONE |
|
|
emailed request for extention
|