BLD97-00943
| INSP - Carpentry | 12/19/1997 | 12/19/1997 | 12/19/1997 12:00:00 AM | A | PART |
|
|
W RUSS & GS AT SITE RE 1HR & PLAN
|
BLD97-01459
| INSP - Letter of compliance | 12/19/1997 | 12/19/1997 | 12/19/1997 12:00:00 AM | A | PASS |
|
|
LC 015502
|
BLD97-01459
| INSP - Final | 12/19/1997 | 12/19/1997 | 12/19/1997 12:00:00 AM | A | PASS |
|
|
NO BOND PER T RECORDS.
|
BLD97-02104
| INSP - Conference | 12/19/1997 | 12/19/1997 | 12/19/1997 12:00:00 AM | A | PASS |
|
|
W/ BOB A.& TOM: CN ON SEISMIC OK AT GRID CLG AT CORR'S
|
BLD97-03114
| INSP - Framing/Rough-in | 12/19/1997 | 12/19/1997 | 12/19/1997 12:00:00 AM | A | PART |
|
|
OK TO INS, NEED TRUSS CALCS
|
BLD97-03114
| INSP - Framing/Rough-in | 12/19/1997 | 12/19/1997 | 12/19/1997 12:00:00 AM | P | PASS |
|
|
COMPLETION OF R-IN, OK TO COVER, CHK'D 1HR
|
BLD97-03115
| INSP - Conference | 12/19/1997 | 12/19/1997 | 12/19/1997 12:00:00 AM | P | PASS |
|
|
RE 1HR REQ'S
|
MEC97-03249
| INSP - Rough-in & Gas Pressure | 12/19/1997 | 12/19/1997 | 12/19/1997 12:00:00 AM | P | PART |
|
|
PART, GAS TEST OK, TOLD TO CALL FOR FINAL WHEN DONE & COMB. AIR INSTALLED...
|
MEC97-03850
| INSP - Gas pressure test | 12/19/1997 | 12/19/1997 | 12/19/1997 12:00:00 AM | P | PASS |
|
|
BY GAS CO; TOLD TO RECALL FOR FIAL, GAS LOG...CHK DAMPER
|
BLD97-00843
| INSP - Final | 12/19/1997 | 12/19/1997 | 12/19/1997 12:00:00 AM | P | PASS |
|
|
REINSPECTION...STRUCT OK NEED ELEC, RECALL OR COME IN FOR LETTER
|
BLD97-02237
| INSP - Framing/Rough-in | 12/19/1997 | 12/19/1997 | 12/19/1997 12:00:00 AM | P | PASS |
|
|
rec'd eng'g, done, ok to cover
|
BLD97-02237
| INSP - Energy code compliance | 12/19/1997 | 12/19/1997 | 12/19/1997 12:00:00 AM | P | PART |
|
|
CHK UNDERFLOOR AT FINAL
|
BLD97-03113
| INSP - Conference | 12/19/1997 | 12/19/1997 | 12/19/1997 12:00:00 AM | P | PASS |
|
|
W/ SUPT RE 1HR
|