Inspections for the day of: Wednesday, December 19, 2012.
Number of inspections: 14
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorTroy Cobbley
TitleFIRE INSPECTOR
Phone #794-9483
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
BLD12-03085 FIRE-Conference12/18/201212/19/201212/20/2012 4:11:31 PMPCANC
Anita Phone #: ###-#### Still waiting for a clarification for the building code officail on the exit hardware.
FIR12-00720 INSP-Sprinkler Rough-in12/19/201212/19/201212/19/2012 3:26:49 PMPPASS
See the city approved plans for areas marked "ok" where piping can be covered.
FIR12-00693 INSP-Sprinkler Rough-in12/19/201212/19/201212/19/2012 3:25:56 PMPPASS
See the city approved plans for the tenant space/residence where the piping rough-in passed. The walkin shower needs to be totally enclosed, as per discussion, or sprinkler protection required. Lonnie is going to move the pendant head over 2" in the master bath so that coverage is provided under the soffit. As per a later telephone dicussion with Lonnie, he is going to add a pendant in the entry way to provide coverage on the far side of a surface mounted light fixture. As-builts will be needed showing these changes and the deletion of one pendant in a storage area that is now a 1/2 bath. Sprinkler piping can not be covered until a tenting inspection has been completed.
FIR12-00661 INSP-Sprinkler Rough-in/Hydro12/19/201212/19/201212/19/2012 3:05:24 PMPFAIL
The overhead hydro tests failed again. A re-inspection fee has been applied. I also noted that the Fire Dept. Connection may be mounted too high as per NFPA 13 A 8.17.2 but hard to tell at this point due to possible site work not being complete.
FIR12-00676 INSP-Sprinkler Rough-in12/19/201212/19/201212/19/2012 2:41:02 PMPPASS
The sprinkler piping can be covered. Joist space has been filled with insulation.
BLD12-03026 FIRE-Conference12/19/201212/19/201212/19/2012 2:40:14 PMPPASS
The sprinkler piping can be covered. Joist space has been filled with insulation.
FIR12-00661 INSP-Sprinkler Rough-in/Hydro12/18/201212/19/201212/19/2012 1:29:58 PMAFAIL
Hydro test failed due to visable leak at the flow switch.
FIR12-00328 INSP-Final Inspection12/18/201212/19/201212/19/2012 12:04:06 PMAFAIL
No city approved drawings on site for review. I noted that the horn/strobes are overspaced. Also missing the breaker locks. The project related FIR permit for the AES could not be finaled due to lack of required Netcon.
FIR12-00327 INSP-Final Inspection12/18/201212/19/201212/19/2012 12:02:28 PMAFAIL
No city approved drawings on site for review. I noted that the singel horn/strobe is mounted too high. Could not verify candella.
FIR12-00163 INSP-Final Inspection12/18/201212/19/201212/19/2012 10:57:03 AMACANC
Could not complete inspection due to problems with the project related fire alarm permits. Also the outside alarm bell needs to be relocated to the side of the building where the FDC has been placed.
FIR12-00416 INSP-Final Inspection12/18/201212/19/201212/19/2012 10:53:28 AMAFAIL
A Netcon 5 or lower is required and we only had a 6 so no additional testing was performed. Correct batteries and panel model is installed.
FIR12-00403 INSP-Final Inspection12/18/201212/19/201212/19/2012 10:46:31 AMAPASS
Permit finaled. Netcon was 5
BLD12-02591 FIRE-Final Inspection12/18/201212/19/201212/19/2012 9:00:51 AMAPASS
Life safety passed
BLD12-02709 FIRE-Final Inspection12/18/201212/19/201212/19/2012 9:00:28 AMAPASS
Life safety passed