Inspections for the day of: Thursday, December 19, 2013.
Number of inspections: 12
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorMike Jordan
TitleBLD-COM/RES INSPECTOR
Phone #794-9473
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
GCB13-00146 GCB-Framing12/18/201312/19/201312/19/2013 4:12:55 PMPFAIL
Chee ###-####. Provide squash blocking under 2nd. floor framing for paralam above to transfer loads. Tighten holddown at5 east wall. Justify openings in inter shear panels. ok to insulate.
BLD13-03388 BLD-Framing/Rough-in12/18/201312/19/201312/19/2013 3:16:36 PMPPASS
Call for access Phone #: 2088708584 >> Inspection requested via mobile web by Jeremy Plantenga
GCB13-00149 GCB-Shearwall12/19/201312/19/201312/19/2013 1:51:55 PMPPASS
Willie ###-####
BLD13-01556 BLD-Wall Bracing12/18/201312/19/201312/19/2013 12:04:30 PMAFAIL
justin Phone #: ###-####. Install all missing blocking and restaple.
BLD13-02582 BLD-Wall Bracing12/18/201312/19/201312/19/2013 12:02:48 PMAPASS
justin Phone #: ###-####
BLD13-02706 BLD-Footing12/18/201312/19/201312/19/2013 11:22:46 AMAPART
kyle Phone #: ###-####. Loading dock footing and grade beam footing at main entry. Pending special inspection. Also went over cold weather conc. with contractor.
BLD13-02706 BLD-Framing/Rough-in12/18/201312/19/201312/19/2013 11:21:14 AMAPASS
kyle Phone #: ###-####. Interior steel stud framed walls (I walls) non moveable ok.
ESC13-01168 Site Preparation12/19/201312/19/201312/19/2013 10:40:08 AMADONE
ESC13-01168 DOC - Permit Finaled12/19/201312/19/201312/19/2013 10:39:58 AMPPASS
BLD13-03198 BLD-Final12/18/201312/19/201312/19/2013 10:39:38 AMAPASS
Korry Phone #: ###-####
BLD13-03198 DOC - Permit Finaled12/19/201312/19/201312/19/2013 10:39:27 AMPPASS
BLD13-01688 BLD-Framing/Rough-in12/18/201312/19/201312/19/2013 10:16:35 AMAPART
CHARLES Phone #: ###-####. Top of wall for firewalls @ corridor on grids H and H.3 from 1 to 3.9 for phase 1 patient addition, pending electrical inspection. Steel stud framing for exterior walls at phase 1 part B. Also noted steel track at phase 1 patient addition has been shot down per the approved engineering.