PLM02-00330
| Final | 12/1/2002 | 12/2/2002 | 12/2/2002 12:00:00 AM | A | PASS |
|
|
Scheduled by a contractor via Hello! on 12/01/2002 at 20:52:42. Contact: ###-####. final ok 12/2/2002 9:25:39 AM
|
PLM02-03601
| Water and/or Sewer | 11/27/2002 | 12/2/2002 | 12/2/2002 12:00:00 AM | A | PASS |
|
|
Scheduled by a contractor via Hello! on 11/27/2002 at 13:22:23. Contact: ###-####. final ok 12/2/2002 9:06:51 AM
|
PLM02-03600
| Water and/or Sewer | 11/27/2002 | 12/2/2002 | 12/2/2002 12:00:00 AM | A | PASS |
|
|
Scheduled by a contractor via Hello! on 11/27/2002 at 13:23:27. Contact: ###-####. final ok 12/2/2002 9:07:04 AM
|
PLM02-03625
| Groundwork | 11/27/2002 | 12/2/2002 | 12/2/2002 12:00:00 AM | P | PART |
|
|
###-#### gw ok they added 2 future restroom ground works on the west side of this job and will need stamped resubmittals for them. 12/2/2002 10:29:44 AM
|
PLM02-03511
| Plumbing Rough-in | 12/2/2002 | 12/2/2002 | 12/2/2002 12:00:00 AM | P | PASS |
|
|
###-#### henry ri ok 12/2/2002 3:26:57 PM
|
PLM02-02941
| Final | 12/2/2002 | 12/2/2002 | 12/2/2002 12:00:00 AM | P | PASS |
|
|
jerry--homeowner will be there; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie final ok 12/2/2002 2:33:10 PM
|
PLM02-03628
| Water and/or Sewer | 12/2/2002 | 12/2/2002 | 12/2/2002 12:00:00 AM | P | FAIL |
|
|
SERINA; Phone #: ###-#### Internet Inspection Request from: Darla Downs sewer to be laid on a firm bed its entire length, roll clamps 180 deg apart by meter, tests ok 12/2/2002 1:42:22 PM
|
PLM02-03096
| Final | 12/2/2002 | 12/2/2002 | 12/2/2002 12:00:00 AM | P | FAIL |
|
|
###-#### KEY ABOVE BOTH ENTRY DOORS pipe water heater pan drain to exterior or garage floor 12/2/2002 2:55:07 PM
|
PLM02-03634
| Water and/or Sewer | 12/2/2002 | 12/2/2002 | 12/2/2002 12:00:00 AM | P | PASS |
|
|
###-####
|
PLM02-03628
| Water and/or Sewer | 12/2/2002 | 12/2/2002 | 12/2/2002 12:00:00 AM | P | PASS |
|
|
they came back before i could get out of the area, sw final ok
|