BLD08-00399
| FIRE-Final Inspection | 12/1/2008 | 12/2/2008 | 12/3/2008 11:05:17 AM | A | PART |
|
|
Per Ken Roule and Mark Sentenno the new area can be occupied until the existing areas have been remodeled and the rest of the construction is completed.
|
FIR08-00748
| INSP-Sprinkler Rough-in/Hydro | 12/2/2008 | 12/2/2008 | 12/2/2008 4:03:36 PM | P | PASS |
|
|
Rough-in and overhead hydro test passed.
|
FIR07-00766
| INSP-Final Inspection | 12/2/2008 | 12/2/2008 | 12/2/2008 4:00:36 PM | P | CANC |
|
|
Phone #: ###-#### Internet Inspection Request from: John Warnick
|
BLD08-00576
| FIRE-Final Inspection | 12/2/2008 | 12/2/2008 | 12/2/2008 2:50:30 PM | P | PASS |
|
|
Life safety passed. The fire hydrant at the property entrance that is mounted too high will be followed up on by the fire dept. Mark Sentenno is aware of the problem.
|
BLD08-01809
| FIRE-Final Inspection | 12/2/2008 | 12/2/2008 | 12/2/2008 2:50:08 PM | P | PASS |
|
|
Life safety passed. The fire hydrant at the property entrance that is mounted too high will be followed up on by the fire dept. Mark Sentenno is aware of the problem.
|
FIR08-00158
| INSP-Sprinkler Rough-in/Hydro | 12/1/2008 | 12/2/2008 | 12/2/2008 1:41:18 PM | A | PASS |
|
|
The underground hydro test passed.
|
FIR08-00741
| INSP-Final Inspection | 12/2/2008 | 12/2/2008 | 12/2/2008 11:09:02 AM | A | PASS |
|
|
Permit finaled
|
FIR08-00701
| INSP-Sprinkler Rough-in/Hydro | 12/2/2008 | 12/2/2008 | 12/2/2008 10:27:08 AM | P | PART |
|
|
24hr air test started at 10:30 with 42 1/2 psi on the guage
|
FIR08-00741
| INSP-Sprinkler Rough-in | 12/1/2008 | 12/2/2008 | 12/2/2008 12:00:00 AM | A | CANC |
|
|
kenny Phone #: ###-####
|