Inspections for the day of: Monday, December 2, 2013.
Number of inspections: 11
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorMike Jordan
TitleBLD-COM/RES INSPECTOR
Phone #794-9473
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
BLD13-01286 BLD-Wall cover12/2/201312/2/201312/2/2013 3:36:29 PMPPART
1st. floor, east central units ok to tape.
BLD13-02056 BLD-Wall Bracing12/2/201312/2/201312/2/2013 3:14:30 PMPPASS
Phone #: ###-#### >> Inspection requested via web by Brian Stark
BLD13-02048 BLD-Wall Bracing12/2/201312/2/201312/2/2013 3:14:10 PMPPASS
Phone #: ###-#### >> Inspection requested via web by Brian Stark
BLD13-02052 BLD-Wall Bracing12/2/201312/2/201312/2/2013 3:13:50 PMPPASS
Phone #: ###-#### >> Inspection requested via web by Brian Stark
BLD13-02050 BLD-Energy code compliance12/2/201312/2/201312/2/2013 3:13:20 PMPPASS
Call brian prior Phone #: ###-#### >> Inspection requested via web by Brian Stark
BLD13-02050 BLD-Framing/Rough-in12/2/201312/2/201312/2/2013 3:12:59 PMPPASS
Call brian prior Phone #: ###-#### >> Inspection requested via web by Brian Stark
ESC13-00747 General Inspection12/2/201312/2/201312/2/2013 1:24:03 PMPPASS
BLD13-02049 BLD-Other11/26/201312/2/201312/2/2013 1:23:39 PMPPART
mike - rebar Phone #: ###-####. Work i progress on reinforcement for concrete tilt panels. Will be ok pending special inspection.
BLD13-01286 BLD-Wall cover11/27/201312/2/201312/2/2013 10:51:49 AMAPART
Center Units first floor Phone #: ###-#### >> Inspection requested via web by Mike McHargue. Work in progress, 1st. floor, center units.
BLD13-01287 BLD-Energy code compliance11/27/201312/2/201312/2/2013 10:45:04 AMANR
air sill Phone #: ###-#### >> Inspection requested via web by Mike McHargue
BLD13-01287 BLD-Framing/Rough-in11/27/201312/2/201312/2/2013 10:43:54 AMANR
Phone #: ###-#### >> Inspection requested via web by Mike McHargue