PLM14-03284
| PLM-Aging Inspection | 12/2/2016 | 12/2/2016 | 12/5/2016 11:43:34 AM | | PEND |
|
|
Spoke with the homeowner. Subdivision is required to install a new water main in the street prior to final.
|
PLM16-04197
| Plumbing Rough-in | 12/1/2016 | 12/2/2016 | 12/5/2016 8:09:01 AM | A | NR |
|
|
JOB WILL BE READY FOR INSPECTION AT 2:30AM. CHRIS IS THE JOB CONTACT ###-#### Phone #: ###-#### Inspection requested via web by BECCA DUMMER
|
PLM16-04197
| Groundwork | 12/1/2016 | 12/2/2016 | 12/5/2016 8:08:38 AM | A | NR |
|
|
JOB WILL BE READY FOR INSPECTION AT 2:30AM. CHRIS IS THE JOB CONTACT ###-#### Phone #: ###-#### Inspection requested via web by BECCA DUMMER
|
PLM16-04393
| Other | 12/2/2016 | 12/2/2016 | 12/2/2016 4:40:37 PM | P | PASS |
|
|
Phone number is for journeyman on project Robert Resue Phone #: ###-#### Inspection requested via web by Erin Whiting.
|
MIS16-00378
| PLM-Conference | 12/1/2016 | 12/2/2016 | 12/2/2016 4:07:57 PM | P | NR |
|
|
Cruben// please call ahead// inspection for occupancy Phone #: ###-####
|
PLM16-04344
| Water Heater Final | 12/2/2016 | 12/2/2016 | 12/2/2016 4:07:27 PM | P | FAIL |
|
|
Install full size shut off valve to the water heater. Ensure the lowest fitting on the t&p has a 1/16" hile drilled into the bottom.
|
PLM16-04344
| Water and/or Sewer | 12/2/2016 | 12/2/2016 | 12/2/2016 4:04:51 PM | P | CANC |
|
|
|
PLM16-03850
| Plumbing Rough-in | 12/2/2016 | 12/2/2016 | 12/2/2016 3:27:14 PM | P | PART |
|
|
Phone #: ###-#### Inspection requested via web by Todd Walter. 60lb gas test pass.
|
PLM16-03199
| Final | 12/1/2016 | 12/2/2016 | 12/2/2016 2:44:59 PM | P | PART |
|
|
Daniel Phone #: ###-####. Gas and water line ok to cover. Need to certify new PVB.
|
PLM16-04385
| Final | 12/2/2016 | 12/2/2016 | 12/2/2016 2:43:56 PM | P | PASS |
|
|
|
PLM16-03753
| Plumbing Rough-in | 12/1/2016 | 12/2/2016 | 12/2/2016 2:41:38 PM | P | FAIL |
|
|
JOB # 50349. Phone #: ###-#### Inspection requested via web by Ann Marie Reyes. Fail water test
|
PLM16-03754
| Plumbing Rough-in | 12/1/2016 | 12/2/2016 | 12/2/2016 2:37:35 PM | P | PASS |
|
|
50347 - NEW RESIDENTIAL PLUMBING INSTALLATION Phone #: ###-#### Inspection requested via web by Ann Marie Reyes
|
PLM16-04391
| Water and/or Sewer | 12/1/2016 | 12/2/2016 | 12/2/2016 2:14:34 PM | P | PASS |
|
|
I will call if I run in to any problems. Starting excavation first thing in the morning and hoping to have it back filled before end of day for safety reasons.( Kids in area) Thank you. Phone #: ###-#### Inspection requested via web by Michael Webb
|
PLM16-04391
| DOC - Permit Finaled | 12/2/2016 | 12/2/2016 | 12/2/2016 2:14:21 PM | P | PASS |
|
|
|
PLM16-03982
| Final | 12/1/2016 | 12/2/2016 | 12/2/2016 1:53:54 PM | A | PASS |
|
|
WHOLE HOUSE REPIPE PLEASE CALL AHEAD ###-#### Phone #: ###-#### Inspection requested via web by Chris Field
|
PLM16-04385
| Water and/or Sewer | 12/1/2016 | 12/2/2016 | 12/2/2016 1:23:14 PM | A | PASS |
|
|
Phone #: ###-#### Inspection requested via web by Vicki Tallent
|
PLM16-04401
| Plumbing Rough-in | 12/2/2016 | 12/2/2016 | 12/2/2016 12:28:17 PM | P | PASS |
|
|
Phone #: ###-#### Inspection requested via web by Ben Taylor
|
PLM16-04371
| Final | 12/1/2016 | 12/2/2016 | 12/2/2016 12:11:26 PM | A | PASS |
|
|
Phone #: ###-#### Inspection requested via web by Mary LaFayette
|
PLM16-04388
| Other | 12/1/2016 | 12/2/2016 | 12/2/2016 11:48:39 AM | A | PART |
|
|
Matt-gas pressure Phone #: ###-####
|
PLM16-04388
| Water and/or Sewer | 12/1/2016 | 12/2/2016 | 12/2/2016 11:48:12 AM | A | PART |
|
|
Matt Phone #: ###-####. 1. Use 30psi guage for 20psi test on the gas line. 2. Plastic gas line bury 18" min. 3. Install a 14 ga. coated tracer wire on the plastic gas line. 4. Protect steal gas line with 20 mil tape to 6" above grade. 5. Certify PVB. 6. OK to cover water line.
|
PLM16-03514
| Final | 12/1/2016 | 12/2/2016 | 12/2/2016 10:44:49 AM | A | FAIL |
|
|
Phone #: ###-#### Inspection requested via web by Jason Gonzalez. 1. Repair walls and seal all shower arm pennitrations. 2. Install hole covers on all unused holes on the kitchen sinks. 3. Unit 104: Repair the leak on the kitchen sink. 4. All appliances with plumbing connections must be install prior to final.
|
PLM16-02996
| Final | 12/2/2016 | 12/2/2016 | 12/2/2016 10:17:13 AM | A | PART |
|
|
Phone #: ###-#### Inspection requested via web by Raul Castanon. 1. Install a backflow device per plans on the dishwasher or an RP. 2. Repair the leak on the water heater. 3. Provide a connection to the chemical feed per plans. 4. Seal all fixtures to the wall.
|
PLM16-04079
| Groundwork | 12/1/2016 | 12/2/2016 | 12/2/2016 9:37:23 AM | A | PASS |
|
|
Phone #: ###-#### Inspection requested via web by PATTY KIRK. North end trunk line only.
|
PLM16-02585
| Final | 12/1/2016 | 12/2/2016 | 12/2/2016 9:21:36 AM | A | PASS |
|
|
Phone #: ###-#### Inspection requested via web by Rod Davey
|
PLM16-03740
| Plumbing Rough-in | 12/1/2016 | 12/2/2016 | 12/2/2016 9:11:32 AM | A | PASS |
|
|
Homeowner will be there 845am, tub rough in Phone #: ###-#### Inspection requested via web by Boe Jares. Connect condensate drain to the 2" standpipe, connect 2" pvc air inlet to the fau combustion air and complete t&p to the standpipe with a 1" airgap.
|