BLD16-02651
| FIRE-Final Inspection | 12/19/2016 | 12/20/2016 | 12/20/2016 3:04:54 PM | A | CANC |
|
|
Ben Phone #: ###-####
|
FIR14-00205
| INSP-Sprinkler Rough-in | 12/16/2016 | 12/20/2016 | 12/20/2016 3:02:20 PM | P | DONE |
|
|
Scott and I met and did a preliminary inspection. The sprinkler system is currently operational. However there have apparently been wall layout and ceiling type changes. There have been pipe routing changes. Combustible spaces have no protection. A full re-submittal is needed to give an accurate representation of the actual wall and piping layout which needs to include new hydraulic calculations.
|
BLD13-02296
| FIRE-Conference | 12/20/2016 | 12/20/2016 | 12/20/2016 1:12:36 PM | P | DONE |
|
|
I spoke to the owner about the outstanding fire life safety items. It appears that the fire extinguishers have been serviced and we are just waiting for the door hardware to be addressed. The owner stated that work should be complete with-in two weeks.
|
FIR16-00670
| INSP-Final Inspection | 12/20/2016 | 12/20/2016 | 12/20/2016 12:39:01 PM | P | FAIL |
|
|
Not all of the work is complete due to no access to rooms due to flooring being installed
|
FIR16-00239
| INSP-Final Inspection | 12/20/2016 | 12/20/2016 | 12/20/2016 10:38:59 AM | P | PASS |
|
|
permit finaled
|
FIR16-00643
| INSP-Final Inspection | 12/20/2016 | 12/20/2016 | 12/20/2016 10:38:42 AM | P | PASS |
|
|
permit finaled
|
BLD16-03569
| FIRE-Final Inspection | 12/19/2016 | 12/20/2016 | 12/20/2016 8:54:15 AM | A | PASS |
|
|
life safety passed
|
BLD16-03568
| FIRE-Final Inspection | 12/19/2016 | 12/20/2016 | 12/20/2016 8:53:56 AM | A | PASS |
|
|
Life safety passed
|
BLD16-02651
| FIRE-Final Inspection | 12/19/2016 | 12/20/2016 | 12/19/2016 12:30:51 PM | A | FAIL |
|
|
Inspection turned into a conference with the contractor. We went over door hardware issues and lack of notes. Missing duct smoke detector and tags on fire extinguishers. Dan Phone #: ###-####
|