FIR16-00088
| INSP-Sprinkler Rough-in | 12/20/2016 | 12/21/2016 | 12/21/2016 2:14:24 PM | P | DONE |
|
|
Request was for a conference, discussed tenting options with project superintendent to keep insulation on top of piping, also to maintain open space pocket between piping and vapor barrier/sheetrock for radiant heat to reach the piping.
|
FIR16-00188
| INSP-Final Inspection | 12/20/2016 | 12/21/2016 | 12/21/2016 1:15:40 PM | P | PASS |
|
|
Final fire sprinkler inspection passed/complete
|
FIR15-00182
| INSP-Final Inspection | 12/21/2016 | 12/21/2016 | 12/21/2016 1:15:19 PM | P | PASS |
|
|
Final underground inspection passed/complete
|
BLD15-02600
| FIRE-Final Inspection | 12/21/2016 | 12/21/2016 | 12/21/2016 1:13:38 PM | A | PASS |
|
|
Fire sprinkler inspection complete, no fire alarm modifications, fire extinguishers are in place with current inspection tags, premise has a knox box. Final life fire safety inspection passed/complete.
|
FIR08-00368
| FIR-Aging Inspection | 12/21/2016 | 12/21/2016 | 12/21/2016 12:36:52 PM | | CANC |
|
|
|
FIR15-00182
| INSP-Supply line flush | 12/20/2016 | 12/21/2016 | 12/21/2016 12:18:21 PM | P | DONE |
|
|
Underground main line flush complete
|
FIR16-00223
| INSP-Supply line flush | 12/21/2016 | 12/21/2016 | 12/21/2016 12:16:30 PM | P | DONE |
|
|
Underground main line flush complete
|
FIR16-00573
| INSP-Sprinkler Rough-in | 12/20/2016 | 12/21/2016 | 12/21/2016 9:08:59 AM | A | PASS |
|
|
Overhead fire sprinkler pipe tenting complete for piping located in attic spaces, piping in attic spaces approved for cover. Material used for tenting is clear plastic sheeting to cover pipe, blow in insulation will be applied at a later date after sheetrock is installed, prefered method for tenting is batting type insulation to help insure R38 stays over the top of fire sprinkler piping and to maintain the clear pocket between the piping and the sheetrock for radiant heat.
|