Inspections for the day of: Thursday, December 22, 2005.
Number of inspections: 7
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorTroy Cobbley
TitleFIRE INSPECTOR
Phone #794-9483
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
FIR05-00263 FIR-Aging Inspection12/22/200512/22/200512/29/2005 9:03:47 AM NR
work is in progress per Matt with ADT
FIR04-00684 INSP-Sprinkler Rough-in12/22/200512/22/200512/23/2005 2:25:24 PMAFAIL
Sprinkler pendants in basement laundry room are overspaced. A separation is needed in the attic area between the washing machines and the open laundry area.
FIR05-00316 INSP-Final Inspection12/22/200512/22/200512/22/2005 3:48:43 PMPFAIL
Need to test recall for elevator, flow switches need readjusted on the east and west systems, test duct detectors, change signals to 4/2 format, finish reviewing notes.
BLD04-02346 FIRE-Conference12/22/200512/22/200512/22/2005 3:37:53 PMPDONE
Scheduled by a contractor via Hello! on 12/22/2005 at 10:35:19 AM. Contact: ###-####.
FIR05-00841 INSP-Sprinkler Rough-in12/21/200512/22/200512/22/2005 2:57:10 PMAFAIL
Provide letter for installation prior to approved plans to bill, resubmit plans with piping changes. No inspection performed.
BLD05-02644 FIRE-Final Inspection12/21/200512/22/200512/22/2005 2:56:23 PMPFAIL
Mount fire extinguisher as discussed, provide 200 degree head above dishwasher, provide all door hardware, remove thumbturn from rear door, test emergency lights/exit signs. Install ceiling tile at sprinkler heads.
FIR05-00198 INSP-Final Inspection12/21/200512/22/200512/22/2005 12:11:52 PMAFAIL
Horns out of sync in the lobbies and the strobes are out of sync between the lobby and the walkways. Need to run the new NAC panel through the hoops, verify signals and get the NFPA 72 forms.