FIR06-00615
| INSP-Final Inspection | 12/21/2006 | 12/22/2006 | 12/26/2006 2:14:47 PM | P | FAIL |
|
|
Project work is not ready for final as requested due to missing ceilings, ceiling tile, escutcheons, safety caps at some heads are not removed. The as-builts for system modifications made at the new stairway will not be accepted as the work performed exceeds the scope of changes allowed to be approved in the field. Submit documents showing modifications for plan review and approval prior to next inspection.
|
BLD06-01188
| FIRE-Final Inspection | 12/22/2006 | 12/22/2006 | 12/26/2006 11:55:00 AM | P | PART |
|
|
Corrections at the 2nd floor have been verified for completion, fire life safety is satisfactory for the second floor perimeter areas.
|
FIR06-00840
| INSP-Final Inspection | 12/21/2006 | 12/22/2006 | 12/25/2006 11:32:22 PM | P | CANC |
|
|
Inspection rescheduled for 12/26.
|
FIR06-00846
| INSP-Sprinkler Rough-in | 12/22/2006 | 12/22/2006 | 12/22/2006 2:35:06 PM | P | PART |
|
|
Overhead sprinkler rough-in is approved for cover at the drop ceiling areas.
|
BLD06-02366
| FIRE-Final Inspection | 12/22/2006 | 12/22/2006 | 12/22/2006 1:26:58 PM | P | PASS |
|
|
Fire life safety is satisfactory, inspection passed.
|
FIR06-00629
| INSP-Final Inspection | 12/18/2006 | 12/22/2006 | 12/22/2006 1:26:02 PM | P | PASS |
|
|
Fire sprinkler final inspection passed, permit finaled.
|
FIR06-00613
| INSP-Final Inspection | 12/22/2006 | 12/22/2006 | 12/22/2006 1:25:21 PM | P | PASS |
|
|
Fire alarm permit finaled.
|
BLD06-03218
| FIRE-Final Inspection | 12/22/2006 | 12/22/2006 | 12/22/2006 11:07:06 AM | P | PASS |
|
|
Corrections for the fire sprinkler system are complete, fire alarm work to replace the painted strobe appliance boxes pending, remainder of fire life safety passed inspection.
|
BLD06-01919
| FIRE-Final Inspection | 12/22/2006 | 12/22/2006 | 12/22/2006 11:02:30 AM | P | PASS |
|
|
Fire life safety for the vanilla shell passed inspection.
|
FIR06-00994
| INSP-Final Inspection | 12/21/2006 | 12/22/2006 | 12/22/2006 10:44:34 AM | A | PASS |
|
|
Fire sprinkler work passed field inspection, permit finaled.
|
FIR05-00271
| INSP-Sprinkler Rough-in/Hydro | 12/20/2006 | 12/22/2006 | 12/22/2006 10:06:35 AM | A | PART |
|
|
Approval for overhead fire sprinkler cover on the first and second floors of building #7 only. Third floor will require an inspeciton for cold cavity protection prior to cover.
|
FIR06-00910
| INSP-Sprinkler Rough-in | 12/21/2006 | 12/22/2006 | 12/22/2006 10:04:04 AM | A | PART |
|
|
Rough-in is okay for cover at the hard lid ceilings on the first and second floors only. Two heads at the 1st floor sushi bar soffit to be added and verified for compliance at the next scheduled inspection.
|