FIR10-00432
| INSP-Final Inspection | 12/22/2010 | 12/22/2010 | 12/23/2010 2:27:18 PM | P | PASS |
|
|
Permit finaled
|
BLD10-02717
| FIRE-Conference | 12/22/2010 | 12/22/2010 | 12/22/2010 2:56:35 PM | P | DONE |
|
|
I found the the existing fire sprinkler system had been rendered inoperative in the north end of the building. I contacted Mark Sentenno and Gordan Goldsmith with the fire dept and let them know the situation. On site I spoke to the general contractor about the situation and he contacted the fire sprinkler contractor who was able to put the entire sprinkler system back in service within acouple of hours.
|
FIR10-00406
| INSP-Final Inspection | 12/21/2010 | 12/22/2010 | 12/22/2010 2:31:21 PM | P | PASS |
|
|
Permit finaled
|
FIR10-00203
| INSP-Sprinkler Rough-in/Hydro | 12/22/2010 | 12/22/2010 | 12/22/2010 2:30:52 PM | P | PART |
|
|
The hydro test passed but I was unable to perform a rough-in inspection due to the latest approved plans were still being reviewed.
|
FIR10-00236
| INSP-Sprinkler Rough-in | 12/22/2010 | 12/22/2010 | 12/22/2010 2:24:59 PM | P | PASS |
|
|
The remaining sprinkler piping can be covered.
|
FIR10-00640
| INSP-Sprinkler Rough-in/Hydro | 12/22/2010 | 12/22/2010 | 12/22/2010 2:23:58 PM | P | PASS |
|
|
The overhead hydro test passed for the new anti-freeze system. The piping in the canopy can be covered.
|
BLD10-02686
| FIRE-Final Inspection | 12/21/2010 | 12/22/2010 | 12/22/2010 9:13:20 AM | A | PART |
|
|
A temporary occupancy was given with Mark Sentenno's permission until the fire alarm permit has been approved, inspected and passed.
|