ELE04-04039
| Electrical Rough-In | 12/22/2004 | 12/23/2004 | 12/23/2004 12:00:00 AM | A | PASS |
|
|
Daryl; Phone #: ###-#### Internet Inspection Request from: Jan Rice ok to cover p/s u/g n ok 12/23/2004 9:53:20 AM
|
ELE04-02595
| Electrical Rough-In | 12/22/2004 | 12/23/2004 | 12/23/2004 12:00:00 AM | A | PART |
|
|
Scheduled by a contractor via Hello! on 12/22/2004 at 11:48:25 AM. Contact: ###-####. 3rd floor so end, rooms ok to cover 12/23/2004 8:12:49 AM
|
ELE04-03257
| Final | 12/22/2004 | 12/23/2004 | 12/23/2004 12:00:00 AM | A | PASS |
|
|
Scheduled by a contractor via Hello! on 12/22/2004 at 2:02:17 PM. Contact: ###-####. called contractor to put fixture in bonus room cubby hole. ok to final 12/23/2004 8:52:59 AM
|
ELE04-04038
| Rough-In Permanent Service | 12/22/2004 | 12/23/2004 | 12/23/2004 12:00:00 AM | A | NR |
|
|
please call 1/2 hr before and Jeremy will meet you there thank you.; Phone #: ###-#### Internet Inspection Request from: Todd Holbrook met with elect, they fixed gndg. Service disconnect has to be labelled. 12/23/2004 9:32:58 AM
|
ELE04-03703
| Final | 12/23/2004 | 12/23/2004 | 12/23/2004 12:00:00 AM | A | PASS |
|
|
have a Merry Christmas; Phone #: ###-#### Internet Inspection Request from: Bob Glenn ok to final 12/23/2004 10:02:43 AM
|
ELE04-04038
| Rough-In Permanent Service | 12/23/2004 | 12/23/2004 | 12/23/2004 12:00:00 AM | A | PASS |
|
|
Corrections made, found label.p/s u/g n ok
|
ELE04-03911
| Temporary Service | 12/23/2004 | 12/23/2004 | 12/23/2004 12:00:00 AM | P | PASS |
|
|
Scheduled by a contractor via Hello! on 12/23/2004 at 8:05:46 AM. Contact: ###-####. t/s u/g n ok 12/23/2004 1:27:35 PM
|
ELE04-04027
| Temporary Service | 12/23/2004 | 12/23/2004 | 12/23/2004 12:00:00 AM | P | PASS |
|
|
Phone #: ###-#### Internet Inspection Request from: Bob Glenn t/s u/g n ok 12/23/2004 12:10:20 PM
|
ELE04-04026
| Temporary Service | 12/23/2004 | 12/23/2004 | 12/23/2004 12:00:00 AM | P | PASS |
|
|
Phone #: ###-#### Internet Inspection Request from: Bob Glenn t/s u/g n ok 12/23/2004 12:19:01 PM
|
ELE04-03962
| Electrical Rough-In | 12/22/2004 | 12/23/2004 | 12/23/2004 12:00:00 AM | P | NR |
|
|
Scheduled by a contractor via Hello! on 12/22/2004 at 2:11:45 PM. Contact: ###-####. met with electrician and discussed adding recpts, stapling romex, nail plates, spacing, grounding. Not ready until next week sometime. 12/23/2004 3:39:26 PM
|